Term
What are the inputs for the 1st process in Project Risk Management? |
|
Definition
1. Project Charter 2. PMP 3. Project Documents 4. EEfs 5. OPAs |
|
|
Term
What are the tools and techniques for the 1st process in Project Risk Management? |
|
Definition
1. Expertise 2. Data Anslysis 3. Meetings |
|
|
Term
What are the outputs for the 1st process in Project Risk Management? |
|
Definition
|
|
Term
What are the inputs for the 2nd process in Project Risk Management? |
|
Definition
1. PMP 2. Project Documents 3. Agreements 4. Procurement Documentation 5. EEfs 6. OPAs |
|
|
Term
What are the tools and techniques for the 2nd process in Project Risk Management? |
|
Definition
1. Expertise 2. Data Gathering 3. Data Analysis 4. Interpersonal and Team Skills 5. Prompt Lists 6. Meetings |
|
|
Term
What are the outputs for the 2nd process in Project Risk Management? |
|
Definition
1. Risk Register 2. Risk Reports 3. Project Documents Updates |
|
|