Term

13KV Site Services

Purpose

Definition
Provides a reliable and backed up source f power to the 13KV Auxiliary Loop Electrical System
Term

13 KV Site Services

 

 Design Basis

Definition

2 Redundant power sources suppling 480/240/120 to:

Salem TSC/B Building/4KV Breaker Shop/Admin Building/Services Building/NOSF/Fab Shop/ Secondary Chemistry Lab/ TP&L Loads

Term
What Bus Group Feeds Switching/Subststions 2,4,5
Definition
Group 3 (8032)
Term
Which Substation/Switching Stations have Key interlocks and Why?
Definition

1 and 5 due to Line of sight seperation between the Switching station and the Substation.

 

6 is the newest style and has a built in Key interlock to ensure disconnects are not opened under load.

Term

Which Substations have forced air cooling for their transformers?

strip Heaters?

How are they powered?

Definition

1,3,5 have cooling fans

all have strip heaters.

Both Fans and strip heaters are powered from 13KV to 120 VAC transformers

Term
automatic recloser function and operation
Definition

Fast acting circuit breaker that is designed to close again to clear non-persistant faults on overhead lines o buses.

Our reclosures have been set up to be a "one shot to lockout". Meaning they will open upon fault and not reclose without manual manipulation

Term
Which two recloser units are set up to open automatically on a loss of supply power?
Definition
Reclosers 1 and 2 will open automatically upon a loss of supply power after a 20 sec time delay
Term
Which Relosers will change their min trip settings when power loss is sensed?
Definition

Reclosers 3/4/5

Settings will reduce from 480a to 240a

Term

What power do the reclosers use to close?

to open?

Definition

AC Power is used to close the reclosers from being energized by either side of the recloser

 

Opening or "Trip" voltage is supplied by a self charged internal DC battery.

Term
Substation 1 Loads
Definition

U1 and U2 Plant computer

Secondary Chem Lab

Admin Telephone(DID)

Cross Flow enclosure

U1 Hydrogen Dryer

Term
Substation 2 Loads
Definition

Maintenance Facilities- Building 470

Maintenance TP&L loads

Term
Substation 3 Loads
Definition
NOSF Building
Term
Substation 4 Loads
Definition

Reverse Osmosis - Demin Plant

SWIS Weld recept.

Term
Substation 5 Loads
Definition

"B" Building/TSC

U1/U2 Containment Maint. Power

Term
Substation 6 Loads
Definition

New Maintenance Shop

Security Vehicle Barrier System