Term
What are the six processes of Project Schedule Management? |
|
Definition
1. Plan Schedule Management 2. Define Activities 3. Sequence Activities 4. Estimate Activity Duration 5. Develop Schedule 6. Control Schedule |
|
|
Term
What are the inputs for the 1st process in Project Schedule Management? |
|
Definition
1. Project Charter 2. PMP 3. EEFs 4. OPAs |
|
|
Term
What are the Tools and Techniques for the 1st process in Project Schedule Management? |
|
Definition
1. Expertise 2. Data Analysis 3. Meetings |
|
|
Term
What are the outputs for the 1st process in Project Schedule Management? |
|
Definition
1. Schedule Management Plan |
|
|
Term
What is the schedule management plan? |
|
Definition
Part of PMP. Establishes how schedule will be developed and maintained |
|
|
Term
What are the two tools and techniques in Project Schedule Management for agile/adaptive environments? |
|
Definition
Rolling wave Planning, Iterative scheduling with backlog, and On-demand (pull-based) |
|
|
Term
What are the inputs for the 2nd process in Project Schedule Management? |
|
Definition
1. PMP - Schedule MP, Development Approach 2. EEFs 3. OPAs |
|
|
Term
What are the Tools and Techniques for the 2nd process in Project Schedule Management? |
|
Definition
1. Expertise 2. Decomposition 3. Rolling Wave Planning 4. Meetings |
|
|
Term
What is decomposition in the Define Activities process? |
|
Definition
It is a technique where each work package Is broken down into activities where the schedule can be estimated. Involve team members. |
|
|
Term
What are the outputs for the 2nd Process in Project Schedule Management? |
|
Definition
1. Activity List 2. Activity Attributes 3. Milestones List 4. Change Requests 5. PMP Updates |
|
|