What are the inputs to the 4th process in Project Schedule Management? |
|
Definition
1. PMP - Schedule MP, Scope Baseline 2. Project Documents 3. EEFs 4. OPAs |
|
|
Term
What are the Tools and Techniques of the 4th process in Project Schedule Management? |
|
Definition
1. Expertise 2. Analogous Estimating 3. Parametric Estimating 4. Three-point estimating 5. Bottom-up estimating 6. Data Analysis 7. Decision Making 8. Meetings |
|
|
Term
What are the outputs of the 4th process in Project Schedule Management? |
|
Definition
1. Duration Estimates 2. Basis of Estimates 3. Project Documents Updates |
|
|
Term
Explain the difference between the different quantitative analysis methods for determining the schedule in the 4th process of Project Schedule Management |
|
Definition
Analogous estimating uses historical data from similar projects to create an estimated schedule. No calculations
Parametric estimating uses common sense. If it takes 1 hour to complete 50 lines of code, it would take 4 hours to complete 200 lines of code
Three-point estimating uses the most likely, pessimistic, and optimistic estimates average.
Bottom-up estimating decomposes WBS activities |
|
|