6.4 - Estimate Activity Durations
6.4
4
Management
Post-Graduate
08/11/2020

Additional Management Flashcards

 


 

Cards

Term
What are the inputs to the 4th process in Project Schedule Management?
Definition
1. PMP - Schedule MP, Scope Baseline
2. Project Documents
3. EEFs
4. OPAs
Term
What are the Tools and Techniques of the 4th process in Project Schedule Management?
Definition
1. Expertise
2. Analogous Estimating
3. Parametric Estimating
4. Three-point estimating
5. Bottom-up estimating
6. Data Analysis
7. Decision Making
8. Meetings
Term
What are the outputs of the 4th process in Project Schedule Management?
Definition
1. Duration Estimates
2. Basis of Estimates
3. Project Documents Updates
Term
Explain the difference between the different quantitative analysis methods for determining the schedule in the 4th process of Project Schedule Management
Definition
Analogous estimating uses historical data from similar projects to create an estimated schedule. No calculations

Parametric estimating uses common sense. If it takes 1 hour to complete 50 lines of code, it would take 4 hours to complete 200 lines of code

Three-point estimating uses the most likely, pessimistic, and optimistic estimates average.

Bottom-up estimating decomposes WBS activities