Term
What is the purpose of the 5th process in Project Schedule Management? |
|
Definition
To analyze activity sequences, durations, resources, and schedule constraints to create a schedule model |
|
|
Term
What are the inputs for the 5th process in Project Schedule Management? |
|
Definition
1. PMP 2. Project Documents 3. Agreements 4. EEFs 5. OPAs |
|
|
Term
What are the tools and techniques for the 5th process in Project Schedule Management? |
|
Definition
1. Schedule Network Analysis (Overarching tool/technique) 2. Critical Path Method 3. Resource Optimization 4. Data Analysis 5. Leads and Lags 6. Schedule Compression 7. PMIS 8. Agile Release Planning |
|
|
Term
Explain Resource Optimization and the two types |
|
Definition
Balancing start/stop of scheduled activities with resource availability 1. Resource Leveling - shifting schedule to meet resource work hours 2. Resource Smoothing - Balancing out resource utilization |
|
|
Term
Explain schedule compression and the two types |
|
Definition
Used to shorten or accelerate schedule duration w/o reducing project scope. 1. Crashing -Adding additional resources 2. Fast-tracking -doing multiple activities in parallel |
|
|
Term
What is agile release planning? |
|
Definition
It is a high level summary timeline of the release schedule for each iteration of the product. |
|
|
Term
What are the outputs for the 5th process in Project Schedule Management? |
|
Definition
1. Schedule Baseline 2. Project Schedule 3. Schedule Data 4. Project Calendars 5. Change Requests 6. PMP Updates 7. Project Documents Updates |
|
|
Term
What is the schedule baseline? |
|
Definition
It is the approved version of a schedule model |
|
|
Term
What is the difference between the project schedule and the project calendar? |
|
Definition
Project schedule - Presents linked activities with planned dates
Project Calendar - Presents work periods/shifts available for scheduled activities. |
|
|
Term
|
Definition
Collection of info to describe and control schedule |
|
|