Term
What is the purpose of the 2nd process in Project Quality Management? |
|
Definition
To Translate Quality Management Plan into executable quality activities that incorporate org's quality policies |
|
|
Term
What are the inputs for the 2nd process in Project Quality Management? |
|
Definition
1. PMP 2. Project Documents 3. OPAs |
|
|
Term
What are the tools and techniques for the 2nd process in Project Quality Management? |
|
Definition
1. Data Gathering 2. Data Analysis 3. Data Representation 4. Decision Making 5. Problem Solving 6. Audits 7 Design for X 8. Quality Improvement Methods |
|
|
Term
What are the outputs for the 2nd process in Project Quality management? |
|
Definition
1. Quality Reports 2. Testing and Evaluation Documents 3. Change Requests 4. PMP Updates 5. PD Updates |
|
|