Term
What is the purpose of the 3rd process in Project Quality Management?
Definition
To record results of Quality activities and verify deliverables do as intended
Term
What are the inputs for the 3rd process in Project Quality Management?
Definition
1. PMP
2. Project Documents
3. Approved Change Requests
4. Deliverables
5. WPD
6. EEFs
7. OPAs
Term
What are the tools and techniques for the 3rd process in Project Quality Management?
Definition
1. Data Gathering
2. Data Analysis
3. Data Representation
4. Testing/Product Evaluation
5. Inspections
6. Meetings
Term
What are the outputs for the 3rd process in Project Quality Management?
Definition
1. Quality Control Measurements
2. Change Requests
3. Work Performance Information
4. PMP Updates
5. PD Updates
6.Verified Deliverables