Term
|
Definition
to be a phased acquisition approach |
|
|
Term
|
Definition
Defense Acquisition Management System |
|
|
Term
For instances where technology is mature a program may be approved as a ____ _____ ____ and enter DAMS at _______ ___ to complete the Integrated System Design process within the Engineering & Manufacturing Development Phase. |
|
Definition
new acquisition program Milestone B |
|
|
Term
|
Definition
Integrated System Design Process |
|
|
Term
|
Definition
Engineering & Manufacturing Development Phase |
|
|
Term
What are the two processes within the EMD Phase? |
|
Definition
|
|
Term
|
Definition
System Capability & Manufacturing Process Demonstration |
|
|
Term
ISD and SCAMPD are part of what phase of DAMS? |
|
Definition
|
|
Term
DAMS is a _____ of activities that represents or describes defense ______ ______. |
|
Definition
continuum acquisition programs |
|
|
Term
DAMS is divided into 3 different activities. |
|
Definition
Pre-Systems Acquisition Systems Acquisition Sustainment |
|
|
Term
What are the two phases of Pre-Systems Acquisition? |
|
Definition
Materiel Solution Analysis Technology Development |
|
|
Term
What marks the end of the Pre-Systems Acquisition activity? |
|
Definition
|
|
Term
How many milestones does DAMS require? |
|
Definition
3 milestones, A, B, and C |
|
|
Term
What phase follows Milestone B? |
|
Definition
Engineering & Manufacturing Development |
|
|
Term
What are the two phases of the Systems Acquisition activity? |
|
Definition
Engineering & Manufacturing Development Production & Deployment |
|
|
Term
What is the final activity and phase of the DAMS? |
|
Definition
Sustainment
Operations & Support |
|
|
Term
The phases that make up Systems Acquisition and Sustainment are divided into 6 work efforts. |
|
Definition
Integrated System Design System Capability & Manufacturing Process Demonstration Low-Rate Initial Production Full-Rate Production & Deployment Sustainment Disposal |
|
|
Term
What determines a new acquisition program's entry point and acquisition path? |
|
Definition
They are determined by assessing the maturity of the relevant technology. |
|
|
Term
What is mandatory for all programs? |
|
Definition
|
|
Term
|
Definition
Materiel Development Decision |
|
|
Term
|
Definition
Milestone Decision Authority |
|
|