Term
C.4-K (Immediate Reactor Shutdown) Immediate Actions |
|
Definition
-
If time permits, then reduce recirc flow to minimum
-
Initiate Manual Reactor Scram, then enter C.4-A
-
Notify Shift Supervision.
|
|
|
Term
C.4-A (Reactor Scram) Immediate Actions |
|
Definition
Place REACTOR MODE switch in SHUTDOWN Determine if all control rods are inserted to or beyond position 04 Notify Shift Supervision.
|
|
|
Term
C.4-F (Rapid Power Reduction) Immediate Actions |
|
Definition
Reduce recirc flow but do not go below 35 Mlb/hr IF core flow is less than 35 Mlb/hr, THEN execute C.4-B.05.01.02.A (Control of Neutron Flux Oscillations) concurrently IF conditions require initiation of manual scram THEN execute C.4.K (Immediate Reactor Shutdown) Notify Shift Supervision.
NOTE: Reducing power with rods is NOT an immediate action. It is a subsequent action and requires the procedure to be out. |
|
|
Term
C.4-B.02.05.A (Loss of RBCCW Flow) Immediate Actions |
|
Definition
Verify a RBCCW pump is running If RBCCW System pressure cannot be restored WITHIN 60 seconds, then perform the following: TRIP the RECIRC PUMPS and execute C.4-B.01.04.B (Trip of Two Recirc Pumps) CLOSE RBCCW drywell isolation valves MO-1426, MO-4229, and MO-4230
Notify Shift Supervision
|
|
|
Term
C.4-B.02.05.B (Leak Into RBCCW) Immediate Actions |
|
Definition
|
|
Term
C.4-B.02.01.A (Loss of Fuel Pool Cooling) Immediate Actions |
|
Definition
|
|
Term
C.4-B.02.04.A (Steam Leaks Outside Primary Containment) Immediate Actions |
|
Definition
Evacuate personnel from affected area (use plant page announcement) Notify Shift Supervision.
|
|
|
Term
C.4-B.03.03.B (Relief Valve Leaking) Immediate Actions |
|
Definition
|
|
Term
C.4-B.03.03.A (Stuck Open Relief Valve) Immediate Actions |
|
Definition
If an SRV indicates OPEN, THEN place switch for the affected SRV at Panel C-03 to OPEN and return to normal position; IF SRV E, G, or H OPEN, THEN perform the following: Place respective switch… at Panel C-03 in CLOSE Place Div II Lo-Lo Set Logic switch (HS-S3B) at Control Room Panel C-253D in BYPASS
Notify Shift Supervision.
|
|
|
Term
C.4-B.01.04.A (Trip of One Recirc Pump) Immediate Actions |
|
Definition
Execute C.4-B.05.01.02.A (Control of Neutron Flux Oscillations) concurrently Notify Shift Supervision.
|
|
|
Term
C.4-B.01.04.B (Trip of Two Recirc Pump) Immediate Actions |
|
Definition
Execute C.4-B.05.01.02.A (Control of Neutron Flux Oscillations) concurrently Notify Shift Supervision.
|
|
|
Term
C.4-B.01.03.A (Loss of CRD Pump Flow) Immediate Actions |
|
Definition
Verify a CRD pump is running Notify Shift Supervision.
|
|
|
Term
C.4-B.03.04.A (Loss of Normal Shutdown Cooling) Immediate Actions |
|
Definition
Notify Shift Supervision of plant conditions. |
|
|
Term
C.4-B.04.01.A (Primary Containment Isolation - Group 1) Immediate Actions |
|
Definition
|
|
Term
C.4-B.04.01.B (Primary Containment Isolation - Group 2) Immediate Actions |
|
Definition
|
|
Term
C.4-B.04.01.C (Primary Containment Isolation - Group 3) Immediate Actions |
|
Definition
|
|
Term
C.4-B.04.01.D (Primary Containment Isolation - Group 4) Immediate Actions |
|
Definition
|
|
Term
C.4-B.04.01.E (Primary Containment Isolation - Group 5) Immediate Actions |
|
Definition
|
|
Term
C.4-B.05.01.02.A (Control of Neutron Flux Oscillations) Immediate Actions |
|
Definition
GENERAL NOTE 1: To determine core flow with only one Recirc pump running, idle loop jet pump flow must be subtracted from the running loop jet pump flow.
GENERAL NOTE 2: During core flow transients, it may take up to two minutes for indicated flow to match actual flow.
IMMEDIATE OPERATOR ACTIONS
-
IF core flow is LESS THAN 35 Mlbm/hr, THEN determine if the stability BUFFER or EXCLUSION regions have been entered.
-
IF neutron flux oscillations are observed for any reason while operating in the stability BUFFER or EXCLUSION regions, THEN initiate a MANUAL REACTOR SCRAM.
-
Notify Shift Supervision.
|
|
|
Term
C.4-B.04.01.G (ECCS Suction Control During LOCA) Immediate Actions |
|
Definition
|
|
Term
C.4-B.04.01.F (Leak Inside Primary Containment) Immediate Actions |
|
Definition
|
|
Term
C.4-B.05.14.A (Earthquake) Immediate Operator Actions |
|
Definition
|
|
Term
C.4-B.05.13.A (Loss of Annunciator) Immediate Operator Actions |
|
Definition
|
|
Term
C.4-B.05.07.A (Loss of Reactor Water Level Control) Immediate Operator Actions |
|
Definition
Control Reactor level in MANUAL using any unlocked FW REG valve M/A station Notify shift supervision
|
|
|
Term
C.4-B.05.09.A (Main Steam Pressure Regulator Failure Causing Reduction in Main Steamline Pressure) Immediate Operator Actions |
|
Definition
|
|
Term
C.4-B.05.09.B (Main Steam Pressure Regulator Failure Causing Increased Pressure) Immediate Operator Actions |
|
Definition
|
|
Term
C.4-B.06.02.04.A (Stator Cooling Water Failure) Immediate Operator Actions |
|
Definition
Verify a Stator Cooling water pump is running IF a total loss of Stator Cooling has occurred AND cooling cannot be immediately restored, THEN initiate a Reactor Scram Notify Shift Supervision
|
|
|
Term
C.4-B.06.03.A ([Degrading] Condenser Vacuum) Immediate Operator Actions |
|
Definition
Reduce reactor power per C.4-F to stablize condenser vacuum Notify shift supervision.
|
|
|
Term
C.4-B.06.03.B (Condenser Tube Leak) Immediate Operator Actions |
|
Definition
|
|
Term
C.4-B.06.04.A ([Reduction] in Circ Water Flow) Immediate Operator Actions |
|
Definition
|
|