Shared Flashcard Set

Details

Cost Management Equations
from Andy Crowe's 'The PMP Exam'
13
Management
Professional
06/20/2012

Additional Management Flashcards

 


 

Cards

Term
Budgeted At Completion (BAC)
Definition
How much was originally planned for this project to cost

No formula - derived by looking at the total budgeted cost for the project
Term
Planned Value (PV or BCWS)
(aka Budgeted Cost of Work Scheduled)
Definition
How much work should have been completed at a point in time based on the plan. Derived by measuring planned work completed at a point in time.

PV = Planned % Complete x BAC
Term
Earned Value (EV or BCWP)
(aka Budgeted Cost of Work Performed)
Definition
How much work was actually completed during a given period of time. Derived by measuring actual work completed at a point in the schedule.

EV = Actual % Complete x BAC
Term
Actual Cost (AC or ACWP)
(aka Actual Cost of Work Performed)
Definition
The money spent during a given period of time.

Sum of the costs for the given period of time.
Term
Cost Variance (CV)
Definition
The difference between what we expected to spend and what was actually spent.

CV = EV - AC
Term
Schedule Variance (SV)
Definition
The difference between where we planned to be in the schedule and where we are in the schedule

SV = EV - PV
Term
Cost Performance Index (CPI)
Definition
The rate at which the project performance is meeting cost expectations during a given period of time.

CPI = EV / AC
Term
Cumulative CPI (CPIc)
Definition
The rate at which the proejct performance is meeting cost expectations from the beginning up to a point in time. CPIc is also used to forecast the project's costs at completion.

CPIc = EVc / ACc
Term
Schedule Performance Index (SPI)
Definition
The rate at which the project performance is meeting schedule expectations up to a point in time.

SPI = EV / PV
Term
Estimate At Completion (EAC)
Definition
Projecting the total cost at completion based on project performance up to a point in time.

EAC = BAC / CPIc
Term
Estimate To Completion (ETC)
Definition
Projecting how much more will be spent on the project, based on past performance.

ETC = EAC - AC
Term
Variance At Completion (VAC)
Definition
The difference between what was budgeted and what will actually be spent.

VAC = BAC - EAC
Term
To-Complete Performance Index (TCPIc)
Definition
Performance that must be achieved in order to meet financial or schedule goals.

TCPIc = (BAC - EV) / Remaining Funds
Supporting users have an ad free experience!