DAU PMT 352B Exam 4 Part I (EVM)
DAU PMT 352B Exam 4 Part 1 (EVM)
74
Other
Graduate
11/06/2011

Additional Other Flashcards

 


 

Cards

Term
Budgeted Cost of Work Scheduled (BCWS)
Definition
Represents the value of work planned to be accomplished.
Term
Budgeted Cost of Work Scheduled (BCWS)
Definition
Also known as Planned Value.
Term
Budgeted Cost of Work Scheduled (BCWS)
Definition
When this is portrayed over the contract period, it equates to the Performance Measurement Baseline (PMB), the time phased budget plan against which contract performance will be measured.
Term
Budgeted Cost of Work Performed (BCWP)
Definition
Also known as Earned Value.
Term
Budgeted Cost of Work Performed (BCWP)
Definition
Represents the value of the work accomplished in relation to the PMB.
Term
Actual Cost of Work Performed (ACWP)
Definition
Acutal cost of work accomplished.
Term
Cost Variance
Definition
BCWP - ACWP
Term
Schedule Variance
Definition
BCWP - BCWS
Term
Cost Peformance Index
Definition
BCWP / ACWP
Term
Schedule Performance Index
Definition
BCWP / BCWS
Term
Estimate at Completion (EAC)
Definition
Actuals to Date + (Remaining Work / Efficiency Factor)
Term
Estimate at Completion (EAC)
Definition
Actuals to Date + Work Remaining / Efficiency Factor)
Term
Actuals to Date
Definition
ACWP cum
Term
Work Remaining
Definition
BAC - BCWPcum
Term
Efficiency (Performance) Factors (various)
Definition

-CPIcum

-Composite (CPIcum * SPIcum )
-3-Period (month)CPI

-6-Period (month)CPI

-Weighted (.8CPIcum +.2SPIcum )

Term
EAC (cum CPI)
Definition
ACWP cum   +  (BAC - BCWP cum) / CPI cum  = BAC / CPI cum
Term
EAC ( Composite)
Definition
ACWP cum  + (BAC - BCWP cum) / (CPI cum * SPIcum)
Term
EAC(3/6 month CPI)
Definition
ACWP(cum)  + (BAC - BCWPcum) / CPI3 mo / 6 mo
Term
EAC (weighted)
Definition
ACWPCUM + (BAC-BCWPCUM) / .8CPICUM + .2SPICUM
Term
If assumption is made that contractor will not use availabile MR to complete contract, what "standard" formula is used to compute EAC?
Definition
AWCPCUM + (BAC-BCWPcum) / "Efficiency Factor"
Term
If assumption is made that contractor will use available MR to complete contract, use the alternative formulat which is considered "a contract level EAC" to compute EAC.
Definition

ACWPcum + (TAB - BCWPcum) / "Efficiency Factor"

 

TAB = BAC + Management Reserve

Term
Estimate at Completion (EAC)
Definition
Estimate of Total Cost Thru any Given Level
Term
Standard Formula
Definition
If assumption is made that contractor will NOT use available MR to complete the contract what formula is used?
Term
Alternative Formula
Definition
If assumption is made that contractor will use available MR to complete the contract what formula is used?
Term
To Complete Performance Index (TCPI)
Definition
Cost efficiency needed from "now" to achieve a specific target cost
Term
Cumulative CPI (CPIcum)
Definition
Tends to be the optimistic estimate
Term
Composite (CPIcum * SPIcum)
Definition
Tends to be the pessimestic estimate; weights cost and schedule equally
Term
Three Period (month) CPI
Definition
shows most current cost performance
Term
Six Period (month) CPI
Definition
shows longer timeframe for cost performance may be more accurate (or less accurate) regarding true tends
Term
Weighted (.8 CPIcum + .2SPIcum)
Definition
Weights cost more than schedule
Term
To Complete Performance Index (TCPI)
Definition
Cost efficiency needed from "now" to Achieve a Specific Target Cost
Term
TCPI
Definition

If assumption is made that contractor will not use available MR to cmplete contract, which standard formula would you use for Cost Efficiency needed from now to achieve a specific Target Cost

______ = Work Remaining / Budget Required = BAC - BCWPcum /

                                                                     EAC target - ACWPcum

 

Term
Contract Level TCPI
Definition

If assumption is made that contractor will use available MR to complete the contract, using following the alternate formula will come up with what?

 

____ = Work Remaining / Budget Required =

TAB - BCWPcum / EAC target - ACWPcum

 

TAB = BAC + Management Reserve

Term
Primary Trip Wires
Definition

-System Indicator - EVM System Certification

-IBR within 6 months of contract award

 -Cost, Schedule, and Technical Risks identifed and quantified at the IBR

Term
Secondary Trip Wires
Definition

-CPI and SPI cum index <.95

-Baseline Execution Index (BEI)=#baseline tasks actually completed / #baseline tasks

-Critical Path Length Index (CPLI) of PMB = (critical path duration + float duration) / critical path duration; cum index <.95)

-To Complete Performance Index (TCPI) = Work Remainig / Cost Remaining; CPI to TCPI delta of >10%

-PMB revisions - compared to monthly PMB value; delta of >5%

-Contract Mods - compared to original base value; delta of >10%

 

Term
CPI and SPI
Definition
.cum index <.95
Term
Baseline Execution Index (BEI)
Definition
#baseline tasks actually completed / #baseline tasks
Term
Crtical Path Length Index (CPLI)of PMB
Definition
(critical path duration + float duration) / critcal path duration;
cum index <.95
Term
To Complete Performance Index (TCPI)
Definition
Work Remaning / Cost Remaining
CPI to TCPI data delta of >10%
Term
PMB Revisions
Definition
Compared to monthly PMB value
Delta of >5%
Term
Contract Mods
Definition
Compared to original base value; delta of >10%
Term
Cost Variance Favorable
Definition
if the CV is 1.02 is it favorable or unfavorable?
Term
Cost Variance Unfavorable
Definition
if the CV is -.99 is it favorable or unfavorable?
Term
Schedule Variance Favorable
Definition
if the SV is 1.02, is it favorable or unfavorable?
Term
Schedule Variance Unfavorable
Definition
if the SV is .99, is it favorable or unfavorable?
Term
Planned Value
Definition
How much work did your plan complete?
Term
Earned Value
Definition
HOw much work did you plan actually complete?
Term
Actual Cost
Definition
How much did it cost to complete the work?
Term
SV = (EV-PV) and SPI = (EV/PV)
Definition
What are the performance measurements for the Control Schedule Process?
Term
EV
Definition
This measurement is the value of work that has been completed to date compared to the budget.
Term
PV is higher than EV
Definition
A negative result from an SV calculation means what?
Term
Budgeted Cost of Work Scheduled (BCWS)
Definition
TIme phased estimated value of planned work through any given WBS Level and time period
Term
Budgeted Cost of Work Scheduled (BCWS)
Definition
Planning Baseline - PMB
Term
Budgeted Cost of Work Performed (BCWP)
Definition
TIme phased estimated value of completed work through any given level and time period
Term
Budgeted Cost of Work Performed (BCWP)
Definition
Work Accomplishment Earned Value
Term
Actual Cost of Work Performed (ACWP)
Definition
TIme phased costs incurred for completed work through any given level and time period
Term
Actual Cost of Work Performed (ACWP)
Definition
Expenditures "Actuals are Actuals"
Term
Budget at Completion (BAC)
Definition
Total estimated value for all work planned through any given level
Term
Budget at Completion (BAC)
Definition
Authorized Work
Term
Estimate at Completion (EAC)
Definition
Indpendent cost estimate to complete all work planned through any given level
Term
Estimate at Completion (EAC)
Definition
Forecast Cost
Term
Schedule Performance Index (SPI)
Definition
Work Accomplishment Efficiency Factor
Term
SPI
Definition
BCWP/BCWS
Term
CPI
Definition
Cost Efficiency Factor
Term
CPI
Definition
BCWP/ACWP
Term
To Complete Performance Index TCPI
Definition
Required Future Cost Efficency
Term
To Complete Performance Index TCPI
Definition
BAC - BCWP / EAC - ACWP
Term
Favorable SPIs
Definition
> 1.0
Term
Unfavorable SPIs
Definition
0.0 to 1.0
Term
SPI
Definition
Equals 1.0 at the end of the contract
Term
Favorable CPIs
Definition
> 1.0
Term
Unfavorable CPIs
Definition
0.0 to 1.0
Term
Estimate at Completion (EAC)
Definition
= Money already spent on project + Money you will spend to complete project
Term
Estimate at Completion (EAC)
Definition
ACWP + (BAC - BCWP) / Performance Factor