DAU352B
DOD Acquisition
40
Other
Graduate
10/19/2011

Additional Other Flashcards

 


 

Cards

Term

List and briefly describe the following integrated architecture products that should be included as part of  the Capability Development Document (CDD): 

AV-1
Definition

 

Overview and Summary Information, includes the scope, purpose, intended users, environment depicted, analytical findings.
Term

List the five key elements comprising the Net-Ready Key Performance Parameter (NR-KPP) and give a brief description of each.

Definition

1.   Compliant Solution Architecture  The Blueprints (Solution Architecture):  Description of the system’s operation, traceable between the views.  Defines end-to-end operational effectiveness for the exchange of information .

2.    Compliant with net-centric data and services strategies Brick & Mortar (Net Centric Data and Services Strategies):  Describes the activities, standards and data strategy required to use, operate maintain and manage the net-centric information environment.

3.    Compliant with applicable Global Interface Grid (GIG) technical guidelines Building Codes (Techncial Standards /Interface):  Set of managed technical interface standards – ensuring visibility and stability to  critical interfaces.

4.    Compliant with DoD Information Assurance (IA) requirements Building Inspector (Information Assurance):  Defense Assurance Certification and Accreditation Process (DIACAP).

5.    Supportability. Utilities. Compliant with supportability requirements to include spectrum utilization and information bandwidth requirements, Selective Availability Anti-Spoofing Module (SAASM) and the Joint Tactical Radio System (JTRS) as applicable.  Verify completion of spectrum availability, electromagnetic compatibility, JTRS usage and GPS Selective Availability Anti-Spoofing Module (SAASM) requirements.

Term
List and briefly describe the following integrated architecture products that should be included as part of the Capability Development Document (CDD):
AV-2
Definition

 

 Integrated Dictionary, the architecture data repository with definitions of all terms used in all products.
Term
List and briefly describe the following integrated
architecture products that should be included as part of
the Capability Development Document (CDD): 
OV-1
Definition

 

High-level Operational Concept Graphic, a high-level graphical/textual description of operational concept.
Term

 

List and briefly describe the following integrated
architecture products that should be included as part of
the Capability Development Document (CDD): 
SV-2
Definition

 

 Systems Communications Description/Services Communications Description includes systems nodes, systems, system items, services and service items and their related communications lay-downs.
Term
List and briefly describe the following integrated
architecture products that should be included as part of
the Capability Development Document (CDD): 
TV-1
Definition

 

Technical Standards Profile, provides the listing of standards that apply to Systems and Services View elements in a given architecture.
Term

Explain the difference between the various views in the solution architecture, that is, between the "all view," "operational view," "system view," and "technical view.“

Definition

Operational View (OV): Describes what needs to be done and who does it, and the information exchanges required

Systems and Services View (SV): Flows from the OV; relates systems, services, and characteristics to operational needs

Technical Standards View (TV): Prescribes the standards and conventions

n  Ensures that a system satisfies a specified set of operational requirements

n  Guidelines upon which engineering specifications are based

n  All View (AV): overarching aspects of an architecture that relate to all three views; sets the scope and context of the architecture

Term

What takes place prior to the Material Solution Analysis (MSA) and then the acquisition process begins?

Definition
JCIDS:  Joint Capabilties Integration Development System
Term
What is Evolutionary Acquisition?
Definition

Capabilitiy delivered in increments (not spirals), recognizing up front need for future capability improvments.

 

Each increment::

 

-depnds on mature technology

-is a military useful and supportable operational capability

-Successive Technology Development Phases may be needed to mature technology for multiple increments

Term
What is the formal entry into the acquisition process?
Definition
MDD:  Material Development Decision
Term
What happens prior to Mileston A?
Definition
AOA
Term
What comes out of the Materiel Solution Analysis?
Definition
ICD:  Initial Capabilties Document
Term

As of Feb 2011, who will do the following:

 

-participate in CDRs 

-prepare an assessment of design maturity and technical risks 

-coordinate these assessments with the PM prior to forwarding the to the MDA?

Definition

The Office of Deputy Assistant Secretary of Defense (Systems Engineering)

 

DASD(SE)

Term
Is required only if PDR comes after Milestone B and duirng the Engineering and Manufacturing Development (EMD)?
Definition

Post PDR Assessment

Post CDR Assessment

Term
What is the formal entry into the acquisition process and is manadatory for all programs?
Definition
MDD: Materiel Development Decision
Term

1.  Who approves the guidance to conduct the AOA, which determines the phase of entry into the process; an designates a lead component?

 

2.  ACAT I programs who provides?

Definition

1.  MDA (Milestone Decision Authority)

 

2.  OSD / PA&E

Term
What is the review that authorizes FRP?
Definition
Full Rate Production (FRP) Decision Review
Term
What are the FIVE Better Buying Power categories?
Definition

1.  Target Affordability and control cost growth.

 

2.  Incentivize productivity and innovation in industry

 

3.  Promote real competition

 

4.  Improve tradecraft in services acquisition

 

5.  Reduce non-productive process and bureaucracy

Term
What are the two documents for document streamlining?
Definition

1.  PDUSD AT&L memo 20 APRIL 2011 - Document Streamlining Program Strategies and SEP

 

2.  PDUSD AT&L memo 14 SEP 2011 - Document Streamling Lifecycle Sustainment Plan

Term
When consistent with technology development phase objectives, associated prototyping activity, an dthe MDA approved TDS, the PM shall plan a ________________________________.
Definition
Preliminary Design Review (PDR) before Milestone B.
Term
If a PDR has not been conducted prior to Milestone B, the PM shall plan for a PDR when?
Definition
After Milestone B - as soon as feasible after program initiation.
Term
S&T Actys, ATDs, JCTDs, qualified prototype projects, joint warfighting experienments occur during what phase of the acquisition process?
Definition

Pre-System Acquisition:  Technology Opportunities

 

Term

-Determines acquisition phase of entry 

-Identifies intial review milestones 

-Designates a Lead DOD component 

-Approves Acquisition Decision Memorandum (ADM)

Definition

MDA:  Milestone Decision Authority

 

ACAT I programs:  OSD, Dir, PA&E

Term
What is the exit criteria for a Materiel Development Decision (MDD)?
Definition

-Intial Capabilities Document (ICD)

 

- Director, CAPE will prepare and approve AOA study guidance

 

-AOA Plan due immediately following MDD

Term
What is the entry criteria into the Materiel Solution Analysis?
Definition

Approved ICD

 

Study guidance for conducting the AOA

Term
What actys occur during the Materiel Solution Analysis (MSA)?
Definition

Conduct AOA

 

Develop Technology Development Strategy (TDS)

 

Draft CDD

Term
What is the exit criteria for the MSA?
Definition
Materiel solution to capability need in ICD recommended by lead component conducting the AOA, and phase-specific exit criteria have been satisfied.
Term

At Milestone A, who approves the following:

 

-Materiel Solution 

-Technology Development Strategy (TDS) 

-Exit criteria for next phase 

-Milestone A Certification (10 USC 2366a) 

-Acquisition Decision Memorandum (ADM)

Definition
MDA:  Milestone Decision Authority
Term
What is the readiness capability required at what milestone?
Definition
TRL6 at MS B (entry)
Term

What acquistion phase?

 

Begin of the phase:  MDA approved materiel solution and TDS, full funding in FYDP and for ACAT I and IA programs:  ICE

Definition
Technology Development
Term
What occurs during the Technolgy Development Phase?
Definition
Competitive Prototyping, Develop Reliablity, Availability, and Maintainabilty (RAM) strategy, conduct PDR
Term

Affordable increment of military useful capaiblty identified

Technolgy demonstrated in relevant environment

manufacturing risks identified

PDR

System or increment ready for production within short time frame (less for weapons systems)

 

Exit Criteria for what Phase?

Definition
Technology Development
Term
What milestone is the APB approved and certifies the program?
Definition
Milestone B
Term

 

“Following the  ____________,the MDA may authorize entry into the acquisition management system at any point consistent with phase-specific entrance criteria and statutory requirements.”

Definition
Materiel Development Decision (MDD)
Term
Description of the system’s operation, traceable between the views.  Defines end-to-end operational effectiveness for the exchange of information
Definition

Compliant Solution Architecture  The Blueprints (Solution Architecture):  .

Term
Describes the activities, standards and data strategy required to use, operate maintain and manage the net-centric information environment.
Definition

 Compliant with net-centric data and services strategies Brick & Mortar (Net Centric Data and Services Strategies): 

Term
Set of managed technical interface standards – ensuring visibility and stability to  critical interfaces.
Definition

Compliant with applicable Global Interface Grid (GIG) technical guidelines Building Codes (Techncial Standards /Interface): 

Term
Compliant with supportability requirements to include spectrum utilization and information bandwidth requirements, Selective Availability Anti-Spoofing Module (SAASM) and the Joint Tactical Radio System (JTRS) as applicable.  Verify completion of spectrum availability, electromagnetic compatibility, JTRS usage and GPS Selective Availability Anti-Spoofing Module (SAASM) requirements.
Definition

Supportability. Utilities.

Term
Set of managed technical interface standards – ensuring visibility and stability to  critical interfaces.
Definition

  Compliant with applicable Global Interface Grid (GIG) technical guidelines Building Codes (Techncial Standards /Interface): 

Term
Defense Assurance Certification and Accreditation Process (DIACAP).
Definition

 Compliant with DoD Information Assurance (IA) requirements Building Inspector (Information Assurance): 

 