Term
Energy and Atmosphere Prerequisite 1 intent |
|
Definition
verify that the buildings energy related systems are installed calibrated and perform up to owners standards |
|
|
Term
Energy and Atmosphere Prerequisite 1 req. |
|
Definition
-name a CxA (2 building of experience, report results to owner, not on design team for over 50,000 sqft) -Owner's Project Requirements and Basis of Design must be completed -develop a commissioning plan -verify installation and performance of systems in building -complete summary commissioning report |
|
|
Term
Energy and Atmosphere Prerequisite 1 submittal |
|
Definition
|
|
Term
Energy and Atmosphere Prerequisite 2 intent |
|
Definition
establish the minimum level of energy efficiency for the proposed building |
|
|
Term
Energy and Atmosphere Prerequisite 2 req. |
|
Definition
meet the mandatory provisions of ASHRAE/IESNA 90.1-2004
AND
prescriptive requirements or performance requirements of ASHRAE/IESNa |
|
|
Term
Energy and Atmosphere Prerequisite 2 submittal |
|
Definition
|
|
Term
Energy and Atmosphere Prerequisite 3 intent |
|
Definition
|
|
Term
Energy and Atmosphere Prerequisite 3 req. |
|
Definition
use refrigerant systems with zero CFC emissions and phase out old systems by the end of project completion |
|
|
Term
Energy and Atmosphere Prerequisite 3 submittal |
|
Definition
|
|
Term
Energy and Atmosphere Credit 1 intent |
|
Definition
achieve increased levels of energy performance above the baseline test from prereq. 1 |
|
|
Term
Energy and Atmosphere Credit 1 req. |
|
Definition
new building- 10.5%-42% @ 3.5% increments (1-10 points)
existing buildings- 3.5%-35% @ 3.5% increments (1-10 points) |
|
|
Term
Energy and Atmosphere Credit 1 submittal |
|
Definition
|
|
Term
Energy and Atmosphere Credit 2 intent |
|
Definition
encourage development of increased levels of on-site renewable energy in order to reduce fossil fuel use |
|
|
Term
Energy and Atmosphere Credit 2 req. |
|
Definition
on-site energy should be between 2.5% and 12.5% increasing at 5% intervals (1-3 points) of the total building annual energy costs |
|
|
Term
Energy and Atmosphere Credit 2 submittal |
|
Definition
|
|
Term
Energy and Atmosphere Credit 3 intent |
|
Definition
begin commissioning process early in the design phase and perform additional activities after systems performance verification is complete |
|
|
Term
Energy and Atmosphere Credit 3 req. |
|
Definition
CxA must be independent from design and construction team -review contractor submittals to make sure they are compliant with OPR and BOD -assure involvement of CxA with the building operations within 10 months after substantial completion of O&M |
|
|
Term
Energy and Atmosphere Credit 3 submittal |
|
Definition
|
|
Term
Energy and Atmosphere Credit 4 intent |
|
Definition
reduce ozone depletion and conform to the Montreal Protocol |
|
|
Term
Energy and Atmosphere Credit 4 req. |
|
Definition
1) Don not use refrigerants
2) elect refrigerant and HVAC&R that minimize emissions of compounds that contribute to ozone depletion and global warming |
|
|
Term
Energy and Atmosphere Credit 4 submittal |
|
Definition
|
|
Term
Energy and Atmosphere Credit 5 intent |
|
Definition
be accountable for the building energy consumption over time |
|
|
Term
Energy and Atmosphere Credit 5 req. |
|
Definition
develop and implement a measurement and verification plan -compliant with option B or option D of IPMVP volume 3
The plan shall go out no less than one year time span |
|
|
Term
Energy and Atmosphere Credit 5 submittal |
|
Definition
|
|
Term
Energy and Atmosphere Credit 6 intent |
|
Definition
encourage the use of a grid source renewable energy technology on a net zero pollution basis |
|
|
Term
Energy and Atmosphere Credit 6 req. |
|
Definition
provide at least 35% of buildings baseline energy by engaging into at least a two-year contract
-defined by Center for Resource Solutions |
|
|
Term
Energy and Atmosphere Credit 6 submittal |
|
Definition
|
|