Shared Flashcard Set

Details

InteriorDesignReferenceManual
Ch.7 Coordination, Budgeting & Scheduling
25
Art/Design
Professional
07/15/2007

Additional Art/Design Flashcards

 


 

Cards

Term
designer/consultant liability
Definition
the designer is the prime consultant and is liable to the owner for the consultant's work
Term
cost influences on budget
Definition
1.construction costs (inc.overhead & profit)
2. furniture, fixtures, & equipment (FF&E)
3. Professional fees
4. Taxes
5. Moving Costs
6. Tel/Data
7. Contingencies (always include 5-10%
8. Optional, financing, may be added to owner's operating budget
9. Optional, inflation factor for larger jobs using past cost index
Term
Items included in FF&E budget
Definition
1. furniture
2. appliances
3. free standing equipment
4. window coverings
5. rugs & mats
6. interior plants/planters
7. lamps
8. artwork
9. accessories
Term
Items included in FF&E budget
Definition
1. furniture
2. appliances
3. free standing equipment
4. window coverings
5. rugs & mats
6. interior plants/planters
7. lamps
8. artwork
9. accessories
Term
Contractor's overhead and profit
Definition
general overhead is the cost of doing business for the gc. project overhead is the money it takes to complete a job (permits, temp. trash, etc.)
total of these two combined can range from 10-20%
Term
contractor's profit
Definition
most variable part of the budget. in most cases, the rainge is between 5 and 15% of the total cost.
Term
budgeting
Definition
budgeting is an ongoing activity, and is revised as decisions are made throughout the project.
Term
square footage method of estimating
Definition
typically the first step in cost estimating. make sure to include profit/overhead, professional fees, contingency, taxes.
Best practice to develop three budgets based on low, medium, and hight cost per sqft so that the client can see the probable range.
Term
parameter method of estimating
Definition
an expanded itemization of construction quantities and furnishings, and assigment of unit costs to these quantities.
Term
matrix costing
Definition
a matrix is drawn with the various alternates along one side and the individual elements that combine to make the total cost of the alternatives along the other side.
Term
allowance
Definition
based on a best guess estimate to cover a particular material where the price cannot be determined. also used in bidding to reserve funds for something that has not been finalized.
Term
allowance in bidding
Definition
the contractor mus add to the allowance the costs for unloading, handling, and installing the allowance items, as well as profit & overhead
Term
detailed quantity takeoffs
Definition
done late in the design & cd production using quoted costs per sf for various items and calculated square footages. typically, gc involved at this point, and available to assist in pricing.
Term
cost information
Definition
realistic cost information is difficult to obtain.
two conditions that must be accounted for are geographical location and inflation, and can be done using published cost indexes.
Term
cost index
Definition
divide the higher city index by the lower city index, multiply that by the base cost.
Term
life cycle cost analysis
Definition
estimated over a length of time called the study period, a method for determining the total cost of a building or building component or system. any residual value of the component value is subtracted from the other costs.
Term
what does life-cycle cost analysis take into account
Definition
the initial costs of the element or system, cost of financing, operation, maintenance, and disposal
Term
where would life cycle cost analysis be useful?
Definition
evaluating energy conservation measures
Term
describe some specific costs that may be evaluated in a LCC analysis, and how these are applied to achieve the final LCC cost.
Definition
1. initial costs, acquisition and installation
2. operational costs for utilities
3. maintenance costs over the length of the study period
4. finance costs, as applicable
5. taxes for initial and operating costs
6. residual value
*these costs are estimated, discounted to their present value to take inflation out of the variable. residual value is then discounted to its present value and subtracted from the total to get the final LCC
Term
what are the two major portions of the schedule, and who is responsible for developing?
Definition
1. design time (designer): production of contract documents, scheduling the ordering, delivery, and installation of furniture
2. construction schedule (contractor): designer typically needs to estimate the entire project schedule to give the client a general idea of total time.
Term
what variables impact the time needed in a design schedule?
Definition
1. size and complexity of the project
2. number of people working on the project. (there is a point where having too many people on a project becomes a management and coordination problem, even on large jobs)
3. abilities and design methodology of the project team.
4. type of client and their decision making and approval process.
5. fixed dates such as move in, agency approval, LED
Term
method of scheduling: bar graph or Gantt chart
Definition
the various activities of the schedule are listed along the vertical axis, and a timeline is extended along the horizontal axis. simple to make and easy to understand, suitable for small to mid size projects.
Term
method of scheduling: CPM chart (critical path method)
Definition
graphically depicts all the tasks required to complete a project, the sequence they must occur, their duration, and their earliest or latest possible starting and finishing time.
also defines the sequence of critical tasks that must be met at a specific time in order to meet the total schedule.
Term
method of scheduling:program evaluation and review technique, or PERT chart
Definition
similiar to CPM, but uses different charting methods.
Term
method of scheduling: full wall schedule
Definition
vertical lines are drawn 5" apart on an entire wall, with the space between each line representing a week. project manager develops a prelim. list of tasks and the individuals responsible for those tasks. each task is written on a 3x5 index card, with one labeled start and one finish. the names of the all the people responsible are placed along the left edge of the chart. each person places their own start and finish next to their tasks to indicate their total needed time within the overall schedule.
Supporting users have an ad free experience!