The processes required to ensure a project team completes a project within an approved budget |
|
|
Term
Tasks of Project Cost MGMT Team (5) |
|
Definition
-Calculate the total cost of undertaking each project activity -Determine the total cost of staff on the project -Monitor the total actual cost vs. forecaset cost -Easily identify current and potential cost overruns -Monitor the consumption rate of the project budget. |
|
|
Term
Three project cost mgmt preocesses |
|
Definition
1. Estimate Costs 2. Determine Budget 3. Control costs |
|
|
Term
|
Definition
1. Rough order of magnitude(ROM)-50-100% from actual cost 2. Budgetary- -10-25% of actual cost 3. Definitive- -5-10% from actual cost |
|
|
Term
|
Definition
Variable-Varies depending on conditions Fixed-Remain constant Indirect-Used for multiple projects Direct-Directly related to project Sunk-should be forgotton |
|
|
Term
Three Tools/Techniques for estimating cost |
|
Definition
1. Top Down: Applying costs based on previous projects 2. Bottom up: Start at lowest level on WBS and estimate cost/duration and work up to create a combined cost forecast. Very accurate for total time/cost. 3. Parametric: Estimates based on historical costs |
|
|