Shared Flashcard Set

Details

NAPS 2019 E series Titles
jnon
27
Other
Not Applicable
10/28/2019

Additional Other Flashcards

 


 

Cards

Term
1-E-0
Definition
Reactor Trip or Safety Injection
Term
1-E-1
Definition
Loss of Reactor or Secondary Coolant
Term
1-E-2
Definition
Faulted Steam Generator Isolation
Term
1-E-3
Definition
Steam Generator Tube Rupture
Term
1-ES-0.0
Definition
Re-Diagnosis
Term
1-ES-0.1
Definition
Reactor Trip Response
Term
1-ES-0.2A
Definition
Natural Circulation Cooldown with CRDM Fans
Term
1-ES-0.2B
Definition
Natural Circulation Cooldown without CRDM Fans
Term
1-ES-0.3
Definition
Natural Circulation Cooldown with Steam Void in Vessel (with RVLIS)
Term
1-ES-0.4
Definition
Natural Circulation Cooldown with Steam Void in Vessel (without RVLIS)
Term
1-ES-1.1
Definition
SI Termination
Term
1-ES-1.2
Definition
Post-LOCA Cooldown and Depressurization
Term
1-ES-1.3
Definition
Transfer to Cold Leg Recirculation
Term
1-ES-1.4
Definition
Transfer to Hot Leg Recirculation
Term
1-ES-1.5
Definition
Transfer from Hot Leg Recirculation to Cold Leg Recirculation
Term
1-ES-3.1
Definition
Post-SGTR Cooldown Using Backfill
Term
1-ES-3.2
Definition
Post-SGTR Cooldown Using Blowdown
Term
1-ES-3.3
Definition
Post-SGTR Cooldown Using Steam Dumps
Term
1-ECA-0.0
Definition
Loss of all AC Power
Term
1-ECA-0.1
Definition
Loss of All AC Power Recovery without SI Required
Term
1-ECA-0.2
Definition
Loss of All AC Power Recovery with SI Required
Term
1-ECA-1.1
Definition
Loss of Emergency Coolant Recirculation
Term
1-ECA-1.2
Definition
LOCA Outside Containment
Term
1-ECA-2.1
Definition
Uncontrolled Depressurization of All Steam Generators
Term
1-ECA-3.1
Definition
SGTR with Loss of Reactor Coolant - Subcooled Recovery Desired
Term
1-ECA-3.2
Definition
SGTR with Loss of Reactor Coolant - Saturated Recovery Desired
Term
1-ECA-3.3
Definition
SGTR without Pressurizer Pressure Control