Term
What are the components of the scope baseline? |
|
Definition
It is the Project Scope Statement, the WBS and the WBS Dictionary. |
|
|
Term
What is the primary output of 'Define Activities'? |
|
Definition
|
|
Term
What is 'rolling wave plan'? |
|
Definition
A form of progressive elaboration planning where the work to be accomplished in the near term is planned in more detail and the work to be accomplished further in the future is planned at a higher level. |
|
|
Term
|
Definition
Precedence Diagramming Method |
|
|
Term
What are the inputs to 'Sequence Activities'? |
|
Definition
|
|
Term
What is the output of 'Sequence Activities'? |
|
Definition
Project Schedule Network Diagrams |
|
|
Term
What does a network diagram show? |
|
Definition
The order in which activites are performed |
|
|
Term
|
Definition
Human Resources, materials, equipment, etc. |
|
|
Term
What is the output of the Estimate Activity Resources? |
|
Definition
Resource Breakdown Structure |
|
|
Term
Estimate Activity Durations produces what? |
|
Definition
Activity Duration Estimates |
|
|
Term
What is the PERT formula? |
|
Definition
Pessimistic + 4X Realistic + Optimistic / 6 |
|
|
Term
What is the advantage of managing critical path? |
|
Definition
Chances of being on time or early are improved. |
|
|
Term
What are crashing estimates? |
|
Definition
Estimating by adding more resources. |
|
|
Term
|
Definition
The amount of time an activity can be delayed without impacting critical path. |
|
|
Term
How much float can the critical path have? |
|
Definition
|
|
Term
What is meant by 'free float'? |
|
Definition
The amount of time something could be delayed without impacting other early start dates. |
|
|
Term
Why would you perform a 'backward pass' |
|
Definition
To calculate late start and late finish. |
|
|
Term
If you had an activity that needs to finish before the next one can begin, what type of dependency are they said to have? |
|
Definition
|
|