LFC - Not only the cost of the
Project but also the Product should be considered while designing the Project
[image] |
|
|
Term
|
Definition
Trying to complete the same Project with the less costly way without reducing the Scope. |
|
|
Term
|
Definition
Monetary risks of the Project
Example: if project takes more than 5 yrs to complete, Co will most likely have a Cost Risk due to inflation. |
|
|
Term
|
Definition
Planning PG - Plan how to manage, monitor, & control the cost of the Project
- The specs about the cost estimates determined
- Cost estimation techniques determined
- Cost monitor & ctrl techniques determined
- Reporting & documenting templates to be used
- Guidelines for developing Proj budget
- Internal funds or financing will be used
- Rules for revising the budget
|
|
|
Term
PLAN COST MANAGEMENT ITTOs |
|
Definition
O: Cost Management Plan
- IN: Project Charter
- Risk Mgmt Plan
- EEFs
- OPAs
- T&T: Expert Judgement
- Data Analyses Techniques
- Meetings
|
|
|
Term
|
Definition
|
|
Term
|
Definition
VARIABLE COST - If cost is related to amount of work / material (fuel, salaries)
FIXED COST - if cost is not related to the amount of work / material (office rent
DIRECT COSTS - cost related directly to the Proj work
INDIRECT COSTS - cost not related to the Proj work |
|
|
Term
|
Definition
Supporting document that provides clear & complete understanding of how the cost estimate was derived (assumptions, risks, constraints, range, etc.)
Information about cost, duration & resource estimates found here
From: Estimate Activity Durations
Estimate Costs
Estimate Activity Resources |
|
|
Term
|
Definition
O: Basis of estimates
Revs in assumption log, LL register, Risk register
IN: Cost Mgmt Plan
Quality Mgmt Plan
Scope Baseline
LL register
Proj Schedule
Risk Register
EEFs & OPAs
T&Ts: Expert Judgement
Estim Tech: Analogous, 1P, 3P, Param, etc.
Data Analysis: Alt, Reserve, Cost of Qlty., etc.
PMIS
Decision Making: Voting
|
|
|
Term
DETERMINE BUDGET DEFINITION |
|
Definition
Process of aggregating (rolling up) the estimated costs of individual activities or work packages to establish an authorized cost baseline. |
|
|
Term
|
Definition
O: Cost Baseline
Project Funding Requirements
Revisions: Cost estimates
Proj Schedule
Risk Register
IN: Cost Mgmt Plan
Resource Mgmt Plan
Scope Baseline
WBS & Dictionary
Cost Estimates
Basis of Estimates
Proj Schedule
Risk Register
Business Case
Benefits Mgmt Plan
Proj Charter
Agreements
EEFs & OPAS
T&Ts: Expert Judgement
Cost Aggregation
Data Analysis - reserve A, etc.
Historical Information Review
Funding Limit Reconciliation
Financing (funding needs)
|
|
|
Term
FORUMLAS: CV, SV, CPI, SPI |
|
Definition
CV (COST VARIANCE) CV = EV - AC
SV (SCHEDULE VARIANCE) = EV - PV
CPI (COST PERF INDEX) = EV / AC
SPI (SCHEDULE PERF INDEX) = EV / PV |
|
|
Term
EAC (ESTIMATE AT COMPLETION) FORMULAS |
|
Definition
EAC=BAC/CPI (CPI is expected to be the same for the remainder of the Proj)
EAC=AC+BAC-EV (If future work will be accomplished at the planned rate)
EAC=AC+[(BAC-EV)/(CPI*SPI)] (if both the CPI and SPI influence the remaining work)
EAC = AC + Bottom-up ETC (If the initial plan is no longer valid) |
|
|
Term
TCPI (TO COMPLETE PERFORMANCE INDEX) FORMULA |
|
Definition
|
|
Term
ETC (ESTIMATE TO COMPLETE) FORMULA |
|
Definition
ETC = EAC - AC
Or simply re-estimate ETC |
|
|
Term
VAC (VARIANCE AT COMPLETION) FORMULA |
|
Definition
|
|
Term
EARNED VALUE ANALYSIS VARIANCE & INDEX INTERPRET |
|
Definition
|
|
Term
|
Definition
O: Work Performance Info
Cost Forecasts
Change Requests
Revs: Cost Mgmt Plan
Cost Baseline
Performance Measurement Baseline
Assumption Log
Cost Estimate
Basis of Estimates
Risk Register
LL Register
IN: Cost Mgmt Plan
Cost Baseline
Performance Measurement Baseline
Work Performance Data
Project Funding Requirements
LL Register
OPAs
T&Ts:
Data Analysis: EV, VAR, Trend, Reserve, etc.
TCPI
PMIS
Expert Judgement
|
|
|
Term
AGILE COST CONSIDERATIONS |
|
Definition
Agile is change & uncertainty driven
Light weight estimation methods are used
Detailed calcs are done in JIT manner
Really only cost is truly fixed, but scope and schedule are flexible |
|
|
Term
TAILORING CONSIDERATIONS FOR COST MGMT |
|
Definition
When determining Cost Mgmt processes to be used we need to consider the following:
- If there are any formal org knowledge mgmt processes we need to follow
- If there are existing processes related to cost estimating & budgeting
- Org processes related to Earned Value Mgmt
- If we are going to use Agile approach
- Existing Org governance |
|
|
Term
PROJECT COST MGMT PROCESSES KA & MAJOR OUTs |
|
Definition
Plan Cost Mgmt (P) - cost mgmt plan
Estimate Costs (P) - cost estimates, BoE
Determine Budget (P) - cost baseline, Proj funding requirements
Control Costs (M&C) - work perf info, cost forecasts |
|
|
Term
STEPs TO FINALIZE THE BUDGET |
|
Definition
Determine Cost Baseline
Determine Cost Budget (add Mgmt Reserve)
Compare with Past Similar Projects
Prepare Cash Flow
Check if Results Satisfy Constraints in P Charter
note: if there are problems use schedule to make changes & satisfy constraints
|
|
|