Term
4.1 Develop Project Charter (Initiating) DESCRIBE/DEFINE |
|
Definition
Developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities. |
|
|
Term
4.2 Develop Project Management Plan (Planning) DESCRIBE/DEFINE |
|
Definition
Defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The project's integrated baselines and subsidiary plans may be included within the project management plan. |
|
|
Term
4.3 Direct and Manage Project Work (Executing) DESCRIBE/DEFINE |
|
Definition
The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project's objectives. |
|
|
Term
4.4 Monitor and Control Project Work DESCRIBE/DEFINE |
|
Definition
The process of tracking, reviewing, and reporting project progress against the performance objectives defined in the project management plan. |
|
|
Term
4.5 Perform Integrated Change Control (Monitoring) DESCRIBE/DEFINE |
|
Definition
Reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. |
|
|
Term
4.6 Close Project or Phase (Closing) DESCRIBE/DEFINE |
|
Definition
Finalizing all activities across all of the Project Management Process Groups to formally complete the phase or project. |
|
|
Term
5.1 Plan Scope Management DESCRIBE/DEFINE |
|
Definition
Creating a scope management plan that documents how the project scope will be defined, validated, and controlled. |
|
|
Term
5.2 Collect Requirements DESCRIBE/DEFINE |
|
Definition
Determining, documenting, and managing stakeholder needs and requirements to meet project objectives. The key benefit is that it provides the basis for defining and managing the project and product scope. |
|
|
Term
5.3 Define Scope DESCRIBE/DEFINE |
|
Definition
Developing a detailed description of the project and product. |
|
|
Term
5.4 Create WBS DESCRIBE/DEFINE |
|
Definition
Subdividing project deliverables and project work into smaller, more manageable components. |
|
|
Term
5.5 Validate Scope DESCRIBE/DEFINE |
|
Definition
Formalizing acceptance of the completed project deliverables. |
|
|
Term
5.6 Control Scope DESCRIBE/DEFINE |
|
Definition
Monitoring the status of the project and product scope and managing changes to the scope baseline. |
|
|
Term
6.1 Plan Schedule Management DESCRIBE/DEFINE |
|
Definition
Establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule. |
|
|
Term
6.2 Define Activities DESCRIBE/DEFINE |
|
Definition
Identifying and documenting the specific actions to be performed to product the project deliverables. |
|
|
Term
6.3 Sequence Activities DESCRIBE/DEFINE |
|
Definition
Identifying and documenting relationships among the project activities. |
|
|
Term
6.4 Estimate Activity Resources DESCRIBE/DEFINE |
|
Definition
Estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity. |
|
|
Term
6.5 Estimate Activity Durations DESCRIBE/DEFINE |
|
Definition
Estimating the number of work periods needed to complete individual activities with estimated resources. |
|
|
Term
6.6 Develop Schedule DESCRIBE/DEFINE |
|
Definition
Analysing activity sequences, durations, resource requirements, and schedule contraints to create the project schedule model. |
|
|
Term
6.7 Control Schedule DESCRIBE/DEFINE |
|
Definition
Monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. |
|
|
Term
7.1 Plan Cost Management DESCRIBE/DEFINE |
|
Definition
Establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. |
|
|
Term
7.2 Estimate Costs DESCRIBE/DEFINE |
|
Definition
Developing an approximation of the monetary resources needed to complete project activities. |
|
|
Term
7.3 Determine Budget DESCRIBE/DEFINE |
|
Definition
Aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. |
|
|
Term
7.4 Control Costs DESCRIBE/DEFINE |
|
Definition
Monitoring the status of the project to update the project costs and managing changes to the cost baseline. |
|
|
Term
8.1 Plan Quality Management DESCRIBE/DEFINE |
|
Definition
Identifying quality requirements and/or standards for the project and its deliverables and documenting how the project will demonstrate compliance with quality requirements and/or standards. |
|
|
Term
8.2 Perform Quality Assurance
DESCRIBE/DEFINE |
|
Definition
Auditing the quality requirements and the results from quality control measurements to ensure that appropriate quality standards and operational definitions are used. |
|
|
Term
8.3 Control Quality
DESCRIBE/DEFINE |
|
Definition
Monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes. |
|
|
Term
9.1 Plan Human Resources Management DESCRIBE/DEFINE |
|
Definition
Identifying and documenting project roles, responsibilities, required skills, reporting relationships, and creating a staffing management plan. |
|
|
Term
9.2 Aquire Project Team DESCRIBE/DEFINE |
|
Definition
Confirming human resource availability and obtaining the team necessary to complete project activities. |
|
|
Term
9.3 Develop Project Team DESCRIBE/DEFINE |
|
Definition
Improving competencies, team member interaction, and overall team environment to enhance project performance. |
|
|
Term
9.4 Manage Project Team DESCRIBE/DEFINE |
|
Definition
Tracking team member performance, providing feedback, resolving issues, and managing changes to optimize project performance. |
|
|
Term
10.1 Plan Communications Management DESCRIBE/DEFINE |
|
Definition
Developing an appropriate approach and plan for project communications based on stakeholder's information needs and requirements, and available organizational assets. |
|
|
Term
10.2 Manage Communications DESCRIBE/DEFINE |
|
Definition
Creating, collecting, distributing, storing, retrieving and the ultimate disposition of project information in accordance with the communications management plan. |
|
|
Term
10.3 Control Communications DESCRIBE/DEFINE |
|
Definition
Monitoring and controlling communications throughout the entire project life cycle to ensure the information needs of the project stakeholders are met. |
|
|
Term
11.1 Plan Risk Management DESCRIBE/DEFINE |
|
Definition
Defining how to conduct risk management activities for a project. |
|
|
Term
11.2 Identify Risks DESCRIBE/DEFINE |
|
Definition
Determining which risks may affect the project and documenting their characteristics. |
|
|
Term
11.3 Perform Qualitative Risk Analysis DESCRIBE/DEFINE |
|
Definition
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact. |
|
|
Term
11.4 Perform Quantitative Risk Analysis DESCRIBE/DEFINE |
|
Definition
Numerically analyzing the effect of identified risks on overall project objectives. |
|
|
Term
11.5 Plan Risk Responses
DESCRIBE/DEFINE |
|
Definition
Developing options and actions to enhance opportunities and to reduce threats to project objectives. |
|
|
Term
11.6 Control Risk DESCRIBE/DEFINE |
|
Definition
Implementing risk response plans, tracking identified risks, monitoring residual risks, identifying new risks, and evaluating risk process effectiveness throughout the project. |
|
|
Term
12.1 Plan Procurement Management DESCRIBE/DEFINE |
|
Definition
Documenting project procurement decisions, specifying the approach, and identifying potential sellers. |
|
|
Term
12.2 Conduct Procurements
DESCRIBE/DEFINE |
|
Definition
Obtaining seller responses, selecting a seller, and awarding a contract. |
|
|
Term
12.3 Control Procurements
DESCRIBE/DEFINE |
|
Definition
Managing procurement relationships, monitoring contract performance, and making changes and corrections as appropriate. |
|
|
Term
12.4 Close Procurements
DESCRIBE/DEFINE |
|
Definition
Completing each project procurement. |
|
|
Term
13.1 Identify Stakeholders
DESCRIBE/DEFINE |
|
Definition
Identifying the people, groups, or organizations that could impact or be impacted by a decision, activity, or outcome of the project; and analyzing and documenting relevant information regarding their interests, involvement, interdependencies, influence, and potential impact on project success. |
|
|
Term
13.2 Plan Stakeholdeer Management DESCRIBE/DEFINE |
|
Definition
Developing appropriate management strategies to effectively engage stakeholdeers throughout the project life cycle, based on the analysis of their needs, interests, and potential impact on project success. |
|
|
Term
13.3 Manage Stakeholder Engagement DESCRIBE/DEFINE |
|
Definition
Communicating and working with stakeholders to meet their needs/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle. |
|
|
Term
13.4 Control Stakeholder Engagement DESCRIBE/DEFINE |
|
Definition
Monitoring overall project stakeholder relationships and adjusting strategies and plans for engaging stakeholders. |
|
|
Term
What is Knowledge Area 4 ? |
|
Definition
Project Integration Management |
|
|
Term
What is Knowledge Area 5? |
|
Definition
|
|
Term
What is Knowledge Area 6? |
|
Definition
|
|
Term
|
Definition
|
|
Term
|
Definition
Project Quality Management |
|
|
Term
|
Definition
Project Human Resource Management |
|
|
Term
|
Definition
Project Communications Management |
|
|
Term
|
Definition
|
|
Term
|
Definition
Project Procurement Management |
|
|
Term
|
Definition
Project Stakeholder Management |
|
|
Term
4. Project Integration Management LIST PROCESSES |
|
Definition
- Develop Project Charter (Initiating)
- Develop Project Management Plan
- Direct and Manage Project Work
- Monitor and Control Project Work
- Perform Integrated Change Control
- Close Project or Phase (Closing)
|
|
|
Term
5. Project Scope Management LIST PROCESSES |
|
Definition
- Plan Scope Management (Planning)
- Collect Requirements (Planning)
- Define Scope (Planning)
- Create WBS (Planning)
- Validate Scope (Monitoring)
- Control Scope (Monitoring)
|
|
|
Term
6. Project Time Management LIST PROCESSES |
|
Definition
- Plan Schedule Management
- Define Activities (Planning)
- Sequence Activities
- Estimate Activity Resources
- Estimate Activity Durations
- Develop Schedule
- Control Schedule (Monitoring)
|
|
|
Term
7. Project Cost Management LIST PROCESSES |
|
Definition
- Plan Cost Management (Planning)
- Estimate Costs (Planning)
- Determine Budget (Planning)
- Control Costs (Controlling)
|
|
|
Term
8. Project Quality Management LIST PROCESSES |
|
Definition
- Plan Quality Management (Planning)
- Perform Quality Assurance (Executing)
- Control Quality (Monitoring)
|
|
|
Term
9. Project Human Resource Management LIST PROCESSES |
|
Definition
- Plan HR Management (Planning)
- Aquire Project Team (Executing)
- Develop Project Team (Executing)
- Manage Project Team
|
|
|
Term
10. Project Communications Management LIST PROCESSES |
|
Definition
- Plan Communications Management (Planning)
- Manage Communications (Executing)
- Control Communications (Monitoring)
|
|
|
Term
11. Project Risk Management LIST PROCESSES |
|
Definition
- Plan Risk Management (Planning)
- Identify Risks (Planning)
- Perform Qualitative Risk Analysis
- Perform Quantitative Risk Analysis
- Plan Risk Responses (Planning)
- Control Risks (Monitoring)
|
|
|
Term
12. Project Procurement Management LIST PROCESSES |
|
Definition
- Plan Procurement Management (Planning)
- Conduct Procurements (Executing)
- Control Procurements (Monitoring)
- Close Procurements (Closing)
|
|
|
Term
13. Project Stakeholder Management LIST PROCESSES |
|
Definition
- Identify Stakeholders (Initiating)
- Plan Stakeholder Management (Planning)
- Manage Stakeholder Engagement (Executing)
- Control Stakeholder Engagement
|
|
|
Term
4.1 Develop Project Charter: Inputs |
|
Definition
- Project Statement of Work (SOW)
- Business case
- Agreements
- Enterprise Environmental Factors
- Organizational process assets -OPA
|
|
|
Term
4.1 Develop Project Charter: Outputs |
|
Definition
|
|
Term
4.1 Develop Project Charter: Tools |
|
Definition
- Expert Judgement
- Facilitation Techniques
|
|
|
Term
4.2 Develop Project Management Plan: Inputs |
|
Definition
- Project Charter
- Outputs from other processes
- Enterprise environmental factors -EEF
- Organizational process assets- OPA
|
|
|
Term
4.2 Develop Project Management Plan: Outputs |
|
Definition
1. Project management plan |
|
|
Term
4.2 Develop Project Management Plan: Tools & Techniques |
|
Definition
- Expert Judgement
- Facilitation techniques
|
|
|
Term
4.3 Direct and Manage Project Work - Inputs |
|
Definition
- Project management plan
- Approved change requests
- Enterprise environmental factor -EEF
- Organizational process assets -OPA
|
|
|
Term
4.3 Direct and Manage Project Work: Tools |
|
Definition
- Expert judgment
- Project Management Information Systems
- Meetings
|
|
|
Term
4.3 Direct and Manage Project Work: Outputs |
|
Definition
- Deliverables
- Work performance data
- Change requests
- Project management plan updates
- Project document updates
|
|
|
Term
4.4 Monitor and Control Project Work: Inputs |
|
Definition
- Project management plan
- Schedule forecasts
- Cost forecasts
- Validated changes
- Work performance information
- Enterprise environmental factors
- Organizational process assets
|
|
|
Term
4.4 Monitor and Control Project Work: Tools |
|
Definition
- Expert judgment
- Analytical techniques
- Project management information systems (PMIS)
- Meetings
|
|
|
Term
4.4 Monitor and Control Project Work: Outputs |
|
Definition
- Change requests
- Work performance reports
- Project management plan updates
- Project document updates
|
|
|
Term
4.5 Perform Integrated Change control: Inputs |
|
Definition
- Project Management Plan
- Work Performance reports
- Change requests
- Enterprise environmental factors
- Organizational process assets
|
|
|
Term
4.5 Perform Integrated Change control: Tools |
|
Definition
- Expert judgement
- Meetings
- Change control tools
|
|
|
Term
4.5 Perform Integrated Change control: Outputs |
|
Definition
- Approved change requests
- Change log
- Project management plan updates
- Project document updates
|
|
|
Term
4.6 Close Project or phase: Inputs |
|
Definition
- Project management plan
- Accepted deliverables
- Organizational process assets
|
|
|
Term
4.6 Close Project or Phase: Tools |
|
Definition
- Expert judgment
- Analytical techniques
- Meetings
|
|
|
Term
4.6 Close Project or Phase: Outputs |
|
Definition
- Final product, service or result transition
- Organizational process assets updates
|
|
|
Term
5.1 Plan Scope Management - Inputs |
|
Definition
- Project Management Plan
- Project Charter
- Enterprise Environmental Factors
- Organizational process assets
|
|
|
Term
5.1 Plan Scope Management - Outputs |
|
Definition
- Scope Management Plan
- Requirements management plan
|
|
|
Term
5.1 Plan Scope Management - Tools & Techniques |
|
Definition
|
|
Term
5.2 Collect Requirements - Inputs |
|
Definition
- Scope management plan
- Requirements management plan
- Stakeholder management plan
- Project charter
- Stakeholder register
|
|
|
Term
5.2 Collect Requirements - Tools & Techniques |
|
Definition
- Interviews
- Focus groups
- Facilitated workshops
- Group creativity techniques
- Group decision making techniques
- Questionnaires and surveys
- Observations
- Prototypes
- Benchmarking
- Context diagrams
- Document analysis
|
|
|
Term
5.2 Collect Requirements - Outputs |
|
Definition
- Requirements documentations
- Requirements traceability matrix
|
|
|
Term
5.3 Define Scope - Inputs |
|
Definition
- Scope management plan
- Project charter
- Requirements documentation
- Organizational process assets
|
|
|
Term
5.3 Define Scope - Tools & Techniques |
|
Definition
- Expert judgment
- Product analysis
- Alternatives generation
- Facilitated workshops
|
|
|
Term
5.3 Define Scope - outputs |
|
Definition
- Project scope statement
- Project documents updates
|
|
|
Term
|
Definition
- Scope management plan
- Project scope statement
- Requirements documentation
- Enterprise environmental factors
- Organizational process assets
|
|
|
Term
5.4 Create WBS - Tools & Techniques |
|
Definition
- Decomposition
- Expert judgment
|
|
|
Term
|
Definition
- Scope baseline
- Project documents updates
|
|
|
Term
5.5 Validate Scope - Inputs |
|
Definition
- Project management plan
- Requirements documentation
- Requirements traceability matrix
- Verified deliverables
- Work performance data
|
|
|
Term
5.5 Validate Scope - Tools & Techniques |
|
Definition
- Inspection
- Group decision-making techniques
|
|
|
Term
5.5 Validate Scope - Outputs |
|
Definition
- Accepted deliverables
- Change requests
- Work performance information
- Project document updates
|
|
|
Term
5.6 Control Scope - Inputs |
|
Definition
- Project management plan
- Requirements documentation
- Requirements traceability matrix
- Work performance data
- Organizational Process Assets
|
|
|
Term
5.6 Control Scope - Tools & Techniques |
|
Definition
|
|
Term
5.6 Control Scope - Outputs |
|
Definition
- Work performance information
- Change requests
- Project management plan updates
- Project document updates
- Organizational process assets updates
|
|
|
Term
6.1 Plan Schedule Management - Input |
|
Definition
- Project management plan
- Project charter
- Enterprise environmental factors
- Organizational process assets
|
|
|
Term
6.1 Plan Schedule Management - Tools |
|
Definition
- Expert judgement
- Analytical techniques
- Meetings
|
|
|
Term
6.1 Plan Schedule Management - Output |
|
Definition
1. Schedule management plan |
|
|
Term
6.2 Define Activities - Input |
|
Definition
- Schedule management plan
- Scope baseline
- Enterprise environmental factors
- Organizational assets
|
|
|
Term
6.2 Define Activities - Tools |
|
Definition
- Decomposition
- Rolling wave planning
- Expert judgement
|
|
|
Term
6.2 Define Activities - Outputs |
|
Definition
- Activity list
- Activity attributes
- Milestone list
|
|
|
Term
6.3 Sequence Activities - Inputs |
|
Definition
- Schedule management plan
- Activity list
- Activity attributes
- Milestone list
- Project scope statement
- Enterprise environmental factors
- Organizational assets
|
|
|
Term
6.3 Sequence Activities - Tools |
|
Definition
- Precedence diagramming method (PDM)
- Dependency determination
- Leads and lags
|
|
|
Term
6.3 Sequence Activities - Outputs |
|
Definition
- Project schedule network diagrams
- Project document updates
|
|
|
Term
6.4 Estimate Activity Resources - Inputs |
|
Definition
- Schedule management plan
- Activity list
- Activity attributes
- Resource calendars
- Risk register
- Activity cost estimates
- Enterprise environmental factors
- Organizational process assets
|
|
|
Term
6.4 Estimate Activity Resources - Tools & Techniques |
|
Definition
- Expert judgment
- Alternative analysis
- Published estimating data
- Bottom-up estimating
- Project management software
|
|
|
Term
6.4 Estimate Activity Resources - Outputs |
|
Definition
- Activity resource requirements
- Resource breakdown structure
- Project document updates
|
|
|
Term
6.5 Estimate Activity Durations - Inputs |
|
Definition
- Schedule management plan
- Activity list
- Activity attributes
- Activity resource requirements
- Resource calendars
- Project scope statement
- Risk Register
- Resource breakdown structure
- Enterprise environmental factors
- Organizational process assets
|
|
|
Term
6.5 Estimate Activity Durations - Tools |
|
Definition
- Expert judgment
- Analogous estimating
- Parametric estimating
- Three-point estimating
- Group decision making techniques
- Reserve analysis
|
|
|
Term
6.5 Estimate Activity Durations -Outputs |
|
Definition
- Activity duration estimates
- Project documents updates
|
|
|
Term
6.6 Develop Schedule -Inputs |
|
Definition
- Schedule management plan
- Activity list
- Activity attributes
- Project schedule network diagram
- Activity resource requirements
- Resource calendars
- Activity duration estimates
- Project scope statements
- Risk register
- Project staff assignments
- Resource breakdown structure
- Enterprise environmental factors
- Organizational process assets
|
|
|
Term
6.6 Develop Schedule - Tools |
|
Definition
- Schedule network analysis
- Critical path method
- Critical chain method
- Resource optimization techniques
- Modeling techniques
- Leads and Lags
- Schedule compression
- Scheduling tool
|
|
|
Term
6.6 Develop Schedule -Outputs |
|
Definition
- Schedule baseline
- Project schedule
- Schedule data
- Project calendars
- Project management plan updates
- Project document updates
|
|
|
Term
6.7 Control Schedule - Inputs |
|
Definition
- Project management plan
- Project schedule
- Work performance data
- Project calendars
- Schedule data
- Organizational process assets
|
|
|
Term
6.7 Control Schedule - Tools |
|
Definition
- Performance reviews
- Project management software
- Resource optimization techniques
- Modeling techniques
- Leads and lags
- Schedule compression
- Scheduling tool
|
|
|
Term
6.7 Control Schedule - Outputs |
|
Definition
- Work performance information
- Schedule forecasts
- Change requests
- Project management plan updates
- Project documents updates
- Organizational process assets updates
|
|
|
Term
7.1 Plan Cost Management - Inputs |
|
Definition
- Project Management Plan
- Project Charter
- Enterprise Environmental Factors
- Organizational process assets
|
|
|
Term
7.1 Plan Cost Management - Tools |
|
Definition
- Expert judgment
- Analytical Techniques
- Meetings
|
|
|
Term
7.1 Plan Cost Management - Output |
|
Definition
|
|
Term
7.2 Estimate Costs - Inputs |
|
Definition
- Cost Management Plan
- Human Resources Management Plan
- Scope Baseline
- Project Schedule
- Risk Register
- Enterprise Organizational Factors
- Organizational process assets
|
|
|
Term
7.2 Estimate Costs - Tools |
|
Definition
- Expert judgment
- Analogous estimating
- Parametric Estimating
- Bottom-up Estimating
- Three point estimating
- Reserve analysis
- Cost of quality
- Project management software
- Vendor bid analysys
- Group decision making techniques
|
|
|
Term
7.2 Estimate Costs - Outputs |
|
Definition
- Activity cost estimates
- Basis of estimates -how, assumptions made, range+-?%
- Project document updates - risk register
|
|
|
Term
7.3 Determine Budget - Inputs |
|
Definition
- Cost management plan
- Scope baseline
- Activity cost estimates
- Basis of estimates
- Project schedule
- Resource calendars
- Risk register
- Agreements
- Organizational process assets
|
|
|
Term
7.3 Determine Budget - Tools |
|
Definition
- Cost aggregation
- Reserve analysis
- Expert judgment
- Historical relationships-parametric estimate
- Funding limit reconciliation
|
|
|
Term
7.3 Determine Budget - Outputs |
|
Definition
- Cost baseline
- Project funding requirements
- Project document updates
|
|
|
Term
7.4 Control Budget - Inputs |
|
Definition
- Project management plan
- Project funding requirements
- Work performance data
- OPA
|
|
|
Term
7.4 Control Budget - Tools |
|
Definition
- Earned Value Management
- Forecasting
- To-Complete Performance Index (TCPI)
- Performance reviews
- Project management software
- Reserve analysis
|
|
|
Term
7.4 Control Budget - Outputs |
|
Definition
- Work performance information
- Cost forecasts
- Change requests
- Project management plan updates
- Project document updates
- OPA updates
|
|
|
Term
8.1 Plan Quality Management - Inputs |
|
Definition
- Project Management plan
- Stakeholder register
- Risk Register
- Requirements documentation
- EEF
- OPA
|
|
|
Term
8.1 Plan Quality Management - Tools |
|
Definition
- Cost-benefit analysis
- Cost of Quality
- Seven basic Quality tools - [Cause-effect diagrams, Flowcharts, Checksheets, Pareto diagram, Histograms, Control Charts, Scatter Diagrams]
- Benchmarking
- Design of Experiments
- Statistical Sampling
- Additional tools - Brainstorming, forcefield analysis, Nominal group technique
- Meetings
|
|
|
Term
8.1 Plan Quality Management - Outputs |
|
Definition
- Quality management plan - How to meet quality requirements
- Process improvement plan - includes ( process boundaries, configuration, metrics, targets for improvement)
- Quality Metrics - measurement values and tolerance- E.G. on-time performance, defect frequency, failure rate, availability, reliability
|
|
|
Term
8.2 Perform Quality Assurance (QA) - Inputs |
|
Definition
- Quality management plan
- Process improvement plan
- Quality metrics
- Quality control measurements
- Project documents
|
|
|
Term
8.2 Perform Quality Assurance - Tools |
|
Definition
- Quality management and control tools- [affinity diagrams, PDPC Process Decision Program Charts, Interrelationship digraphs, Tree diagrams, Prioritization matrices, Activity network diagrams, matrix diagams]
- Quality Audits - identify good practices and share industry best practices. Confirm implementation of change requests
- Process analysis - follow steps in Process improvement plan
|
|
|
Term
|
Definition
- Change requests
- Project management plan updates
- Project document updates
- OPA updates
|
|
|
Term
8.3 Control Quality - Inputs |
|
Definition
- Project management plan
- Quality metrics
- Quality checklists
- Work performance data
- Approved change requests
- Deliverables
- Project documents
- OPA
|
|
|
Term
8.3 Control Quality - Tools |
|
Definition
- Seven basic quality tools
- Statistical sampling
- Inspection
- Approved change request review
|
|
|
Term
8.3 Control Quality - Outputs |
|
Definition
- Quality control measurements
- Validated changes
- Verified deliverables
- work performance information - WPI
- Change requests
- Project management plan updates
- OPA updates
|
|
|
Term
9.1 Plan Human Resource Management - Inputs |
|
Definition
- Project management plan
- Activity resource requirements
- EEF
- OPA
|
|
|
Term
9.1 Plan Human Resource Management - Tools |
|
Definition
- Org Charts & Position descriptions
- Networking to find staff
- Organizational theory
- Expert judgment
- Meetings
|
|
|
Term
9.1 Plan Human Resource Management - Outputs |
|
Definition
- Human Resources Management Plan
|
|
|
Term
9.2 Aquire Project Team - Inputs |
|
Definition
- Human Resources Management Plan
- EEF
- OPA
|
|
|
Term
9.2 Aquire Project Team - TOOLS |
|
Definition
- Pre-assignment
- Negotiation
- Acquisition
- Virtual Teams
- Multi-criteria decision analysis
|
|
|
Term
9.2 Aquire Project Team - Outputs |
|
Definition
- Project staff assignments
- Resource Calendars
- Project management plan updates
|
|
|
Term
9.3 Develop Project Team - Inputs |
|
Definition
- Human Resources management plan
- Project staff assignment
- Resource calendars
|
|
|
Term
9.3 Develop Project Team - Tools |
|
Definition
- Interpersonal skills
- Training
- Team-building activities
- Ground rules
- Colocation
- Recognition and rewards
- Personnel assessment tools
|
|
|
Term
9.3 Develop Project Team - outputs |
|
Definition
- Team performance assessments
- EEF updates
|
|
|
Term
9.4 Manage Project Team - Inputs |
|
Definition
- Human resources management plan
- Project staff assignments
- Team performance assessments
- Issue log
- Work performance reports
- OPA
|
|
|
Term
9.4 Manage Project Team - Tools |
|
Definition
- Observation and conversation
- Project performance appraisals
- Conflict management
- Interpersonal skills
|
|
|
Term
9.4 Manage Project Team - outputs |
|
Definition
- Change requests
- Project management plan updates
- Project document updates
- EEF updates
- OPA updates
|
|
|
Term
10.1 Plan communications management - Inputs |
|
Definition
- Project management plan
- Stakeholder register
- EEF
- OPA
|
|
|
Term
10.1 Plan Communications Management - tools |
|
Definition
- Communications requirements analysis
- Communications technology
- Communications models
- Communications methods - Push, pull, Interactive
- Meetings
|
|
|
Term
10.1 Plan Communications management - outputs |
|
Definition
- Communications management plan
- Project document updates - schedule & stakeholder register
|
|
|
Term
10.2 Manage communications - inputs |
|
Definition
- Communications management plan
- work performance reports
- EEF
- OPA
|
|
|
Term
10.2 Manage communications - tools |
|
Definition
- Communications technology
- Communications models
- Communications methods
- Information management systems
- Performance Reporting
|
|
|
Term
10.2 Manage communications - output |
|
Definition
- Project communications
- Project management plan updates
- Project document updates
- OPA updates
|
|
|
Term
10.3 Control Communications - inputs |
|
Definition
- Project management plan
- Project communications
- Issue log
- Work performance data
- OPA
|
|
|
Term
10.3 Control Communications - tools |
|
Definition
- Information management systems
- Expert judgment
- Meetings
|
|
|
Term
10.3 Control communications - outputs |
|
Definition
- Work performance information
- Change requests
- Project management plan updates
- Project document updates
- OPA updates
|
|
|
Term
11.1 Plan Risk Management - inputs |
|
Definition
- Project management plan
- Project charter
- Stakeholder register
- EEF
- OPA
|
|
|
Term
11.1 Plan Risk Management - Tools |
|
Definition
- Analytical techniques
- Expert judgment
- Meetings
|
|
|
Term
11.1 Plan Risk Management - outputs |
|
Definition
|
|
Term
11.2 Identify Risks - Inputs |
|
Definition
- Risk management plan
- Cost management plan
- Schedule management plan
- Quality management plan
- Human resources management plan
- Scope baseline
- Activity cost estimates
- Activity duration estimates
- Stakeholder register
- Project documents
- Procurement documents
- EEF
- OPA
|
|
|
Term
11.2 Identify Risks - tools |
|
Definition
- Documentation Reviews
- Information gathering techniques
- Checklist analysis
- Assumptions analysis
- Diagramming techniques
- SWOT analysis
- Expert judgment
|
|
|
Term
11.2 Identify Risks - output |
|
Definition
|
|
Term
11.3 Perform Qualitative Risk analysis - Inputs |
|
Definition
- Risk management plan
- Scope baseline
- Risk Register
- EEF
- OPA
|
|
|
Term
11.3 Perform Qualitative Risk analysis - Tools |
|
Definition
- Risk probability and impact assessment
- Probability and impact matrix
- Risk data quality assessment
- Risk categorization
- Risk urgency assessment
- Expert judgment
|
|
|
Term
11.3 Perform Qualitative Risk analysis - Outputs |
|
Definition
- Project document updates - Risk register
|
|
|
Term
11.4 Perform Quantitative Risk analysis - Inputs |
|
Definition
- Risk Management Plan
- Cost Management Plan
- Schedule Management Plan
- Risk Register
- EEF
- OPA
|
|
|
Term
11.4 Perform Quantitative Risk analysis -tools |
|
Definition
- Data gathering and representation techniques
- Quantitative risk analysis and modeling techniques. e.g. Sensitivity analysis, EMV, Monte Carlo
- Expert judgment
|
|
|
Term
11.4 Perform Quantitative Risk analysis -outputs |
|
Definition
- Project document updates -
- Probalistic analysis of the project
- Probability of achieving cost & time objectives
- Prioritized list of quantified risks
- Trends in quantitative risk analysis results
|
|
|
Term
11.5 Plan Risk Responses -inputs |
|
Definition
- Risk Management Plan
- Risk Register
|
|
|
Term
11.5 Plan Risk Responses- tools |
|
Definition
- Strategies for negative risk or threats
- Strategies for positive risk or opportunities
- Contingient response strategies
- Expert judgment
|
|
|
Term
11.5 Plan Risk Responses - outputs |
|
Definition
- Project management plan updates
- Project document updates
|
|
|
Term
11.6 Control Risks - Inputs |
|
Definition
- Risk management plan
- Risk register
- Work performance data
- Work performance reports
|
|
|
Term
11.6 Control Risks - Tools |
|
Definition
- Risk reassessment
- Risk audits
- Variance and trend analysis
- Technical performance measurement
- Reserve analysis
- Meetings
|
|
|
Term
11.6 Control Risks - Outputs |
|
Definition
- Work performance information
- Change requests
- Project management plan updates
- Project document updates
- Organizational process assets updates
|
|
|
Term
12.1 Plan Procurement Management - Inputs |
|
Definition
- Project management plan
- Requirements documentation
- Risk Register
- Activity Resource requirements
- Project Schedule
- Activity Cost Estimates
- Stakeholder register
- EEF
- OPA
|
|
|
Term
12.1 Plan Procurement Management - tools |
|
Definition
- Make-or-buy analysis
- Expert judgment
- Market research
- Meetings
|
|
|
Term
12.1 Plan Procurement Management- outputs |
|
Definition
- Procurement management plan
- Procurement Statement of Work
- Procurement documents
- Source Selection criteria
- Make-or-buy decisions
- Change requests
- Project document updates
|
|
|
Term
12.2 Conduct Procurements - inputs |
|
Definition
- Procurement management plan
- Procurement documents
- Source selection criteria
- Seller proposals
- Project documents
- Make-or-buy decisions
- Procurement Statement of Work
- OPA
|
|
|
Term
12.2 Conduct Procurements - tools |
|
Definition
- Bidder conference
- Proposal evaluation techniques
- Independent estimates
- Expert judgment
- Advertising
- Analytical techniques
- Procurement negotiations
|
|
|
Term
12.2 Conduct Procurements - outputs |
|
Definition
- Selected Sellers
- Agreements
- Resource calendars
- Change requests
- Project management plan updates
- Project document updates
|
|
|
Term
12.3 Control Procurements - inputs |
|
Definition
- Project management plan
- Procurement documents
- Agreements
- Approved change requests
- Work performance reports
- Work performance data
|
|
|
Term
12.3 Control Procurements - tools |
|
Definition
- Contract change control system
- Procurement performance reviews
- Inspections and audits
- Performance reporting
- Payment systems
- Claims administration
- Records management systems
|
|
|
Term
12.3 Control Procurements - outputs |
|
Definition
- Work performance information
- Change requests
- Project management plan updates
- Project document updates
- OPA updates
|
|
|
Term
12.4 Close Procurements - inputs |
|
Definition
- Project management plan
- Procurement documents
|
|
|
Term
12.4 Close Procurements - tools |
|
Definition
- Procurement audits
- Procurement negotiations
- Records management system
|
|
|
Term
12.4 Close Procurements - outputs |
|
Definition
- Closed procurements
- OPA updates
|
|
|
Term
13.1 Identify Stakeholders- Inputs |
|
Definition
- Project Charter
- Procurement documents
- Enterprise Environmental factors
- Organizational Process assets
|
|
|
Term
13.1 Identify Stakeholder - Tools |
|
Definition
- Stakeholder analysis
- Expert judgment
- Meetings
|
|
|
Term
13.1 Identify Stakeholder - outputs |
|
Definition
|
|
Term
13.2 Plan Stakeholder Management - inputs |
|
Definition
- Project management plan
- Stakeholder register
- EEF
- OPA
|
|
|
Term
13.2 Plan Stakeholder Management - Tools |
|
Definition
- Expert judgment
- Meetings
- Analytical techniques
|
|
|
Term
13.2 Plan Stakeholder Management - Outputs |
|
Definition
- Stakeholder management plan
- Project document updates
|
|
|
Term
13.3 Manage Stakeholder Engagement - inputs |
|
Definition
- Stakeholder management plan
- Communications management plan
- Change log
- OPA
|
|
|
Term
13.3 Manage Stakeholder Engagement- tools |
|
Definition
- Communications methods
- Interpersonal skills
- Management skills
|
|
|
Term
13.3 Manage Stakeholder Engagement - outputs |
|
Definition
- Issue log
- Change requests
- Project management plan updates
- Project document updates
- OPA updates
|
|
|
Term
13.4 Control Stakeholder Engagement - inputs |
|
Definition
- Project management plan
- Issue log
- Work performance data
- Project documents
|
|
|
Term
13.4 Control Stakeholder Engagement - tools |
|
Definition
- Information management systems
- Expert judgment
- Meetings
|
|
|
Term
13.4 Control Stakeholder Engagement - outputs |
|
Definition
- Work performance information
- Change requests
- Project management plan updates
- Project document updates
- OPA updates
|
|
|