Term
Name the 6 Rating Systems open to registration. |
|
Definition
LEED For New Construction v2.2 LEED for Core and Shell v2.0 LEED for Commercial Interiors v2.0 LEED for Existing Buildings: Operations and Maint. LEED for Schools LEED for Homes |
|
|
Term
What is the flat fee paid up front at time of registration? |
|
Definition
Members: $450 Non-Members: $600 |
|
|
Term
How long does a project team have to submit an appeal? |
|
Definition
|
|
Term
How much does an appeal cost? |
|
Definition
Appeal Cost is $500 / Credit. |
|
|
Term
What needs to be submitted with an appeal? |
|
Definition
Original, re-submittal and appeal documentation. |
|
|
Term
What information should you include with your LEED Application? |
|
Definition
Rating System for which you are submitting Total Projected Score Complete List of all CIRs used, including dates of applied rulings Drawings and photos illustrative of the project (Site plan, floor plan, sections, elevation, rendering) A Check to USGBC |
|
|
Term
If a Multi-Family Residential project is between 4 and 6 stories which Rating Systems can it use? |
|
Definition
LEED for Homes OR LEED for New Construction |
|
|
Term
What Rating System would a K-12 School Have to use? |
|
Definition
LEED for Schools As of April 20, 2007, K-12 Facilities seeking LEED Certification must use the LEED for School. LEED for New Construction can no longer be used. |
|
|
Term
What is the certification fee based on? |
|
Definition
Which Rating system is being applied for Size of the project Member or Non-member |
|
|
Term
What abilities does the administrator have with LEED-Online? |
|
Definition
Can add members to the project team. Assign credits to appropriate individuals. Submit a project to USBGC for Review. |
|
|
Term
What are the SF Thresholds used to determine the certification fees, and which ones use a fixed Rate? |
|
Definition
Less than 50,000 sf (Fixed Rate) 50,000 sf to 500,000 sf (Rate Based on SF) More than 500,000 sf (Fixed Rate) |
|
|
Term
How much does an expedited review cost? |
|
Definition
These are in addition to regular review fees: $5,000 each for Design or Construction Reviews $10,000 for Combined Design & Const. Review Appeal Review $500 + $500 extra LEED EB expedited review fees are $10,000 each for Initial cert. and recert. reviews |
|
|
Term
When and what can be submitted for the Preliminary Construction Phase Review? |
|
Definition
Preliminary Const. Review can take place After Substantial Completion. All attempted construction and/or NEW Design credits and prerequisites. |
|
|
Term
What type of rebates will a project receive for earning LEED Platinum status? |
|
Definition
The Project would receive rebates for Certification Fees Registration Fees, Appeal Review Fees, and any Expiditing Fees will not be refunded. |
|
|
Term
What will be the date of the official certification of a LEED project? |
|
Definition
The date that USGBC receives notice of a project team's acceptance of the Final LEED Review. |
|
|
Term
How many different countries around the world have LEED projects in process? |
|
Definition
41 including Canada, Brazil, Mexico, and India |
|
|
Term
What are the thresholds for the different levels of LEED Certification? |
|
Definition
Certified (26-32 points) Silver (33-38 points) Gold (39-51 points) Platinum (52-69 points) |
|
|
Term
Which review period contains the least amount of days? |
|
Definition
The Final Design-Phase, Construction-Phase, and Combined Final for by USGBC is 15 days. Expediting review periods cuts them from 25 days to 12; and from 15 days to 7. |
|
|