Term
Step 1
Definition
At 15 minutes stand by, Prep flag will be placed at the Dip
Term
Step 2
Definition
Once ceased pumping, conduct gravity drain
Term
Step 3
Definition
Pass to the Bridge “Unrep Complete”
Term
Step 4
Definition
Commence Derigging
Term
Step 5
Definition
Release Probe
Term
Step 6
Definition
Request to De-Tension Span Wire
Term
Step 7
Definition
Trip pelican hook on Delivery Ship’s signal
Term
Step 8
Definition
Ease Span Wire over the side
Term
Step 9
Definition
Once clear of deck edge, Let GO
Term
Step 10
Definition
Pass to the Bridge “All Lines Clear”