Shared Flashcard Set

Details

Simulator
IOP-4
9
Other
Professional
09/29/2013

Additional Other Flashcards

 


 

Cards

Term

 

IOP-4: Power Operations

 

Definition

Purpose: To provide the instructions necessary to vary plant load from 20-100% power, determine the rate of power ascension, and establish steady state operation.

 

Operational Mode: Mode 1 is defined as Keff³0.99, thermal power >5% and TAVG³350°F.

 

Term
IOP Precaustions and Limitations:
Definition

When > P-2 {PT-505 > 15%, 1oo1, enables auto rod withdrawal}, auto rod control should be maintained except for adjustments to AFD, load changes, or IAW approved procedures.

  • Compare NI power to DT for detection of miscalibration of the NIs.
  • With Feedwater Crossflow valid correction factor:
    Average power level over a 1 hour period should not exceed 100% (3459 MWt
    )
  • Without Feedwater Crossflow valid correction factor:
    Average power level over a 1 hour period should not exceed 98.6% (3411 MWt
    )
  • Another CP bed must be put in service every 20%.
  • If Thermal Power change exceeds 15% of RTP within 1 hr period, then inform chemistry to obtain RCS samples between 2-6 hrs.  (R16 and R41 readings required.)
  • Operation without Crossflow (or with an invalid CF) shall not exceed 24 hours; if unavailable > 20 hours, restore with a valid CF within 4 hrs, or lower power < 98.6% within that 4 hours.

To prevent adjusting power into an overpower condition, the following rules are to be adhered to:

 

·   The NCO willensure PT505, PT506, and Average ΔT Power do NOT exceed the values specified in S2.RE‑RA.ZZ‑0011, Tables (these parameters are NOT affected by feedwater nozzle fouling).  A +0.3°F tolerance for ΔT and +3.5 psia tolerance for PT505/PT506 is allowed, which corresponds to 0.5% power.

·   The CRS is aware that the following are known to cause defouling of the feedwater nozzles.

·                  Notification from Chemistry of Feedwater/Condensate chemistry transients including ph, oxygen, iron, and chemical treatment.

·                  Reactor power change of >5% from full power.

 

Term
Tech Specs:
Definition

TS 3.4.9: RCS specific activity is limited to £1.0mCi/gm and £100/E mCi/gm.  An isotopic analysis for Iodine including I-131, I-133, & I-135 2-6 hours following a power change exceeding 15% in one hour.
Basis: Limits ensure that the 2 hour dose at the site boundary will not exceed a small fraction of the Part100 limits.  The 2-6 hour requirement is based on the detection and collection of data concerning Iodine spiking.

 

TS 3.3.1.1: Calorimetric required at least once per 24 hrs when >15% RTP.  At least one calorimetric must be performed between 50-90% RTP.
Basis: Ensure PRNI accurate within 2% at 100% RTP.

 

TS 3.1.1.4: Maintain temperature greater than minimum temperature for criticality (≥541°F).
Bases: This limitation ensures: (1) MTC is within analyzed range, (2) protective instrumentation within normal operating range, (3) the P-12 {Tave < 543°F, 2oo4, Allows manual block of HI Steam Flow SI, Enables Group I Steam Dumps} interlock above allowable setpoint, (4) PZR is capable of being operable with a steam bubble, and (5) pressure vessel above minimum RTNDT
temperature.

 

Power ascension limits: Limits are imposed to prevent the adverse effects of pellet – clad interaction (PCI).  This is of great concern following refueling since handling of the fuel could cause some pellet misalignment and possible clad contact.

 

  • Control rod motion should be minimized during the post-refueling startup.  When >50% power the withdrawal rate is limited to 3 %/hour for heights at which the rods have not been previously positioned (post-refueling).

 

Term
Equipment Operation During Ascension:
Definition

 

Start with:

  • Group busses transferred
  • 2 CN pumps in service, 1 SGFP in service

 

Equipment Operation During Ascension:

 

  • >20% turbine load -                   place BSCDT pumps in service
  • 25-30% reactor power -             shut MS7s
  • Prior to 40% -                           evaluate MSR auto operation
  • >40% reactor power -                place second SGFP in service

 

·        ³40% turbine load -                   ensure A-36: AMSAC BYPASSED alarm clear, begin heater drain pump cleanup

 

  • prior to exceeding 50% -           perform AFD & QPTR calculations
  • >50% -                                      place HDPs in service
  • ³70% -                                      verify SGFP runback armed
  • ³75% -                                      start third condensate pump
  • < 89.5% -                                  ensure PT.TRB-0003 performed
  • < 90% -                                     reevaluate MSRs, Calorimetric if not yet performed
  • 98 - 98.6% -                              verify Feedwater Crossflow System

 

Term
Equipment Operation During Downpower:
Definition

 

  • Rapid load reductions, ≥5%/min, require use of AB.LOAD-0001
  • Transfer Group Busses
  • Stabilize <20% Rx power and go to IOP-5

 

Term

 

Constant Load Operation:

 

Definition

 

  • Set EHC setter to 66% and
  • VLV POS CNTRL ramp rate to 15%/minute
  • TURB INLET PRESS CNTRL ramp rate to 15%/minute

 

Term
Cross Flow
Definition

Allows operation above 98.6% 3411MWt

 

3hrs 20 mins to of data collection > 85% for valid Correction Factor before assending to 3411

 

 

Term

 

Fuel Conditioning / Ramp Rates (NF-AP-440)

 

Definition

 

Not fully Conditioned:

0-40% - no limits

40-72% - 3% per hour

               72-100% - .5% per hour

 

Fully Conditioned: operated at that power level or higher for a total of 72 hours within a 7-day period

 

0-40% - no limits

40-72% - 3% per hour

72-90% - 2% per hour

 

90-100% - 1% per hour

 