Shared Flashcard Set

Details

TECH SPECS CUMULATIVE
ILT '09
19
Other
Not Applicable
01/06/2008

Additional Other Flashcards

 


 

Cards

Term
Tech Spec 3.4.9 LCO (and Applicability) and one hour (or less) Actions.
Definition
"RCS pressure, RCS temperature, RCS heatup and cooldown rates, and the recirc pump starting temperature requirements shall be maintained within limits (at all times). CONDITION A: Req'ts of LCO not met in Mode 1, 2, or 3. ACTION A.1: Restore parameters within limits WITHIN 30 MINUTES. CONDITION C: Req'ts of LCO not met in other than MODES 1,2 or 3. ACTION C.1 Initiate action to restore parameter(s) to within limits IMMEDIATELY."
Term
Tech Spec 3.1.1 LCO/Applicability and Conditions with less than or equal to one hour completion time
Definition
"Section 3.1: Reactivity Control Systems ; Tech Spec 3.1.1: Shutdown Margin; LCO 3.1.1: Shutdown Margin shall be: a. Greater than or equal to 0.38% delta-k per k, with the highest worth control rod analytically determined; or b. greater than or equal to 0.28% delta-k per k, with the highest worth control rod determined by test. APPLICABILITY: Modes 1, 2, 3, 4 and 5; CONDITION C: Shutdown Margin not within limits in MODE 3; REQUIRED ACTION C.1: Initiate action to fully insert all insertable control rods. COMPLETION TIME: Immediately. CONDITION D: Shutdown Margin not within limits in MODE 4. REQUIRED ACTIONS: D.1: Initiate action to fully insert all insertable control rods. COMPLETION TIME: Immediately. AND D.2: Initiate action to resotre secondary containment to OPERABLE status; COMPLETION TIME: 1 hour AND D.3 Initiate action to restore one standby gas treatment subsystem to OPERABLE status. COMPLETION TIME: 1 hour AND D.4: Initiate action to resotre isolation capability in each required secondary containment penetration flow path not isolate. COMPLETION TIME: 1 hour. CONDITION E. Shutdown Margin not within limits in MODE 5. REQUIRED ACTIONS: E.1: Suspend CORE ALTERATIONS except for control rod insertion and fuel assembly removal. COMPLETION TIME: Immediately AND E.2: Initiate action to fully insert all insertable control rods in core cells containing one or ore fuel assemblies. COMPLETION TIME: Immediately AND E.3: Initiate action to restore seoncdary containment to OPERABLE status. COMPLETION TIME: 1 hour AND E.4 Initiate action to restore one SGT subsystem to OPERABLE status. COMPLETION TIME: 1 hour AND #.5 Initiate action to restore isolation capability in each required secondary containment penetration flow path not isolate. COMPLETION TIME: 1 hour."
Term
Tech Spec 3.1.2 LCO/Applicability and Conditions with less than or equal to one hour completion time
Definition
Section 3.1: Reactivity Control Systems; Tech Spec 3.1.2: Reactivity Anomalies; LCO 3.1.2: The reactivity difference between the monitored control rod inventory and the predicted control rod inventory shall be within plus or minus 1% delta-k per k.
Term
Tech Spec 3.1.3 LCO/Applicability and Conditions with less than or equal to one hour completion time
Definition
"Section 3.1: Reactivity Control Systems; Tech Spec 3.1.3: Control Rod OPERABILITY; LCO 3.1.3 Each control rod shall be OPERABLE. APPLICABILITY: MODES 1 and 2. CONDITION A: One withdrawn control rod stuck. REQUIRED ACTIONS: --NOTE-- Rod Worth Minimizer may be bypassed, if required, to allow continued operation. A.1 Verify stuck control rod criteria are met. COMPLETION TIME: Immediately. AND... (not 1 hour or less)... "
Term
Tech Spec 3.1.4 LCO/Applicability and Conditions with less than or equal to one hour completion time
Definition
"Section 3.1: Reactivity Control Systems; Tech Spec 3.1.4: Control Rod Scram Times; LCO 3.1.4: a. No more than 8 OPERABLE control rods shall be ""slow,"" in accordance with Table 3.1.4-1, and b. No more than 2 OPERABLE control rods that are ""slow"" shall occupy adjacent locations. APPLICABILITY: MODES 1 and 2."
Term
Tech Spec 3.1.5 LCO/Applicability and Conditions with less than or equal to one hour completion time
Definition
"Section 3.1: Reactivity Control Systems; Tech Spec 3.1.5: Control Rod Scram Accumulators; LCO 3.1.5: Each control rod scram accumulator shall be OPERABLE. APPLICABILITY: MODES 1 and 2. CONDITION B: Two or more control rod scram accumulators inoperable with reactor steam dome pressure greater than or equal to 900 psig. ACTIONS: B.1 Restore charging water header pressure to greater than or equal to 940 psig. COMPLETION TIME: 20 minutes from discovery of Condition B concurrent with charging water header pressure less than 940 psig. AND --B.2.1 NOTE-- Only applicable if the associated control rod scram time was within the limits of Table 3.1.4-1 during the last scram time Surveillance. Declare the associated control rod scram time ""slow"" OR B.2.2 Declare the associated control rod inoperable. Both Completion times are 1 hour. CONDITION C: One or more control rod scram accumulators in operable with reactor steam dome pressure less than 900 psig. REQUIRED ACTIONS: C.1 Verify all control rods associated with inoperable accumulators are fully inserted. COMPLETION TIME: Immediately upon discovery of charging water header pressure less than 940 psig. AND CONDITION C.2: Declare the associated control rod inoperable. COMPLETION TIME: 1 hour. CONDITION D: Required Action B.1 or C.1 and associated Completion Time not met. REQUIRED ACTION: --NOTE-- Not applicable if all inoperable control rod scram accumulators are associated with fully inserted control rods. Place the reactor mode switch in the shutdown position. COMPLETION TIME: Immediately."
Term
Tech Spec 3.1.7 LCO/Applicability and Conditions with less than or equal to one hour completion time
Definition
Section 3.1:Reactivity Control Systems; Tech Spec 3.1.7:Standby Liquid Control (SLC); LCO 3.1.7: Two SLC subsystems shall be OPERABLE; NO 1 HOUR OR LESS ACTIONS.
Term
Tech Spec 3.1.8 LCO/Applicability and Conditions with less than or equal to one hour completion time
Definition
Section 3.1: Reactivity Control Systems; Tech Spec 3.1.8: Scram Discharge Volume Vent and Drain Valves; LCO 3.1.8: Each Scram Discharge Volume Vent and Drain valve shall be OPERABLE; APPLICABILITY: MODES 1 and 2.
Term
Tech Spec 3.3.1.1 LCO/Applicability and 1 hour or less actions
Definition
"Section 3.3: Instrumentation; Tech Spec 3.3.1.1: RPS Instrumentation; LCO The RPS Instrumentation for each function in Table 3.3.1.1-1 shall be operable. APPLICABILITY: According to Table 3.3.1.1-1. Conditions requiring 1 hour or less actions: C. Condition: One or more functions with RPS trip capability not maintained. Required Action: C.1 Restore RPS trip capability. Completion Time: 1 hour. Condition D: Required Action and associated Completion time of condition A, B, or C not met. Action D.1: Enter the Condition referenced in Table 3.3.1.1-1 for the channel. Completion time: IMMEDIATELY. Condition H: As required by Required Action D.1 and referenced in Table 3.3.1.1-1. Action H.1: Initiate action to fully insert all insertable control rods in core cells containing one or more fuel assemblies. "
Term
Tech Spec 3.3.3.1 LCO/Applicability and 1 hour or less actions
Definition
Section 3.3: Instrumentation; Tech Spec 3.3.3.1: Post Accident Monitoring (PAM) Instrumentation; LCO: The PAM Instrumentation for each Function in Table 3.3.3.1-1 shall be OPERABLE. Applicability: MODES 1 and 2. Condition B: Required action and associated completion time of condition A not met. Action B.1: Initiate action in accordance with Spec 5.6.4. Completion time: IMMEDIATELY. Condition D: Required Action and associated Completion time of Condition C not met. Action D.1: Enter the condition referenced in Table 3.3.3.1-1 for the channel. Completion Time: IMMEDIATELY. Condition F: As required by Required Action D.1 and referenced in Table 3.3.3.1-1. Action: Initiate action in accordance with Specification 5.6.4. Completion Time: IMMEDIATELY
Term
Tech Spec 3.3.4.1 LCO/Applicability and Conditions with less than or equal to one hour completion time
Definition
Section 3.3: Instrumentation; Tech Spec 3.3.4.1: Anticipated Transient Without Scram Recirculation Pump Trip (ATWS-RPT) Instrumentation; LCO 3.3.4.1: Two Channels per trip system for each ATWS-RPT instrumentation Function listed below shall be OPERABLE>: a. Reactor Vessel Water Level - low low; and b. Reactor Vessel Steam Dome Pressure - High; CONDITION C. Both Functions with ATWS-RPT trip capability not maintained; Required Action C.1 Restore ATWS-RPT trip capability for one Function; COMPLETION TIME: 1 hour.
Term
Tech Spec 3.3.5.1 LCO/Applicability and 1 hour or less actions
Definition
"Section 3.3 Instrumentation; Tech Spec 3.3.5.1: Emergency Core Cooling System (ECCS); LCO: The ECCS instrumentation for each Function in Table 3.3.5.1-1 shall be operable. Applicability: According to table 3.3.5.1-1. NOTE: There are 7 Conditions which have 1 hour or less actions. Due to the web of notes and multiple actions required for each condition, this is not conducive to an index card of its own."
Term
Tech Spec 3.3.6.1 LCO/Applicability and 1 hour or less actions
Definition
Section 3.3 Instrumentation; Tech Spec 3.3.6.1: Primary containment isolation Instrumentation; LCO: The primary containment isolation instrumentation for each Function in Table 3.3.6.1-1 shall be OPERABLE. Applicability: According to Table 3.3.6.1-1. Condition B: One or more Functions with primary containment isolation capability not maintained. Action B.1: Restore primary containment isolation capability. Completion time: 1 hour; Condition C: Require Action and associated Completion Time of Condition A or B not met. Action C.1: Enter the Condition referenced in Table 3.3.6.1-1 for the channel. Completion Time: Immediately. Condition F. As required by Required Action C.1 and referenced in Table 3.3.6.1-1. Action: Isolate the affected penetration flow path(s). Competion time: 1 hour. Condition H: As required by Required Action C.1 and referenced in Table 3.3.6.1-1. Action H.1 Declare associated SLC subsystem inoperable in 1 hour. OR Action H.2: Isolate the Reactor Water Cleanup System in hour. Condition I: As req'd by Req'd Action C.1 and referenced in Table 3.3.6.1-1. Required Action I.1: Initiate action to restore channel to OPERABLE status IMMEDIATELY. OR Required Action I.2 Initiate action to isolate teh RHR Shutdown Cooling System IMMEDIATELY.
Term
Tech Spec 3.3.6.1 LCO/Applicability and Conditions with less than or equal to one hour completion time
Definition
Section 3.3:Instrumentation; Tech Spec 3.3.6.1:Primary Containment Isolation Instrumentation; LCO 3.3.6.1: The primary containment isolation instrumentation for each Function in Table 3.3.6.1-1 shall be OPERABLE; APPLICABILITY According to Table 3.3.6.1-1: CONDITION B: One of more Functions with primary containment isolation capability not maintained; REQUIRED ACTION B.1:Restore primary containment isolation capability. COMPLETION TIME: 1 hour. Condition C: Required Action and associated Completeion Time of Condition A or B not met. REQUIRED ACTION: Enter the Condition referenced in Table 3.3.6.1-1 for the channel. COMPLETION TIME: Immediately. CONDITION F: As required by Required Action C.1 and refereneced in Table 3.3.6.1-1; REQUIRED ACTION F.1 Isolate the affected penetration flow path(s); COMPLETION TIME: 1 hour. CONDITION H: As required by Required Action C.1 and referenced in Table 3.3.6.1-1. REQUIRED ACTION(s) H.1 Declare associated SLC subsystem inoperable; COMPLETION TIME: 1 hour. __OR__ H.2: Isolate the RWCU system; COMPLETION TIME: 1 hour. CONDITION I As required by Required Action C.1 and referenced in Table 3.3.6.1-1. REQUIRED ACTIONS: I.1: Initiate action to restore channel to OPERABLE status. COMPLETION TIME: Immediately. __OR__ I.2 Initiate action to isolate the RHR Shutdown Cooling System. COMPLETION TIME: Immediately.
Term
Tech Spec 3.4.1 LCO/Applicability and Conditions with less than or equal to one hour completion time
Definition
"Section 3.4: RCS; Tech Spec 3.4.1: Recirculation Loops Operating; LCO 3.4.1: Two recirc loops with matched flows shall be in operation within the Normal Region of the power to flow map specified in the COLR; OR One recirc loop shall be in operation within the Normal Region of the power to flow map specified in the COLR and with the following limits applied when the associated LCO is applicable: a) LCO 3.2.1 ""APLHGR"", single loop operation limits specified in the COLR; b) LCO 3.2.2, ""MCPR"", single loop operation limits specified in the COLR; and c) LCO 3.3.1.1 ""RPS"" Function 2.a (APRM Flow Referenced Neutron Flux - High High), Allowable Value of Table 3.3.1.1-1 is reset for single loop operation. NOTE: Operation within the Stability Buffer Region of the power to flow map specified in the COLR is allowed provided the power distribution controls specified in the COLR are in effect. APPLICABILITY: Modes 1 and 2. CONDITION A: Operation within Stability Exclusion Region of the power to flow map specified in the COLR. OR Operation within the stability buffer region of the power to flow map specified in the COLR and the power distribution controls specified in the COLR not in effect. REQUIRED ACTION A.1: Initiate action to restore operation to within the Normal Region of the power to flow map specified in the COLR. COMPLETION TIME: Immediately."
Term
Tech Spec 3.4.10 LCO (and Applicability) and one hour or less Actions
Definition
The reactor steam dome pressure shal be less than or equal to 1025.3 psig. (in modes 1 and 2) CONDITION: Reactor steam dome pressure not within limit. ACTION: Restore to within limit WITHIN 15 MINUTES.
Term
Tech Spec 3.4.2 LCO (and Applicability)
Definition
All jet pumps shall be operable (in Modes 1 and 2)
Term
Tech Spec 3.4.2 LCO/Applicability and Conditions with less than or equal to one hour completion time
Definition
Section 3.4: RCS; Tech Spec 3.4.2: Jet Pumps; LCO 3.4.2: All jet pumps shall be OPERABLE; APPLICABILITY: Modes 1 and 2.
Term
Tech Spec 3.4.4 LCO (and Applicability)
Definition
"RCS operational LEAKAGE shall be limited to: a. No pressure boundary leakage; b. Less than or equal to 5 gpm unidentified leakage; c. less than or equal to 25 gpm total leakage averaged over the previous 24 hour period; and d. less than 2 gpm increase in unidentified leakage within the previous period in Mode 1. (applicability: Modes 1, 2 and 3"
Supporting users have an ad free experience!